On November 23, 2026, Applied Digital announced that it has entered into a new 18-year lease agreement with a tier-one investment-grade hyperscaler for 150 megawatts of critical IT capacity. The lease provides for approximately $5.4 billion in base-term contracted revenue, or approximately $12.7 billion if all renewal options are exercised over a 33-year total term. With this addition, the company’s total contracted base-term lease revenue exceeds $41 billion — approximately $100 billion if all renewal options are exercised — across a portfolio of more than 1.6 gigawatts of contracted critical IT load and 2.2 gigawatts of grid-connected peak load. About 75 percent of that contracted base-term revenue is now attributable to investment-grade customers.
The market’s verdict arrived within hours. Applied Digital’s shares rose more than 20 percent on Monday, rebounding from near a 52-week low of $11.31. It is worth asking what exactly the market was buying. The answer is not a data center. No building tied to this lease exists yet, and no rent has been paid. What the market bought was a contract — a promise of $5.4 billion, spread over 18 years, from a tenant whose name the company did not disclose.
That is the story of this deal, and of the three stories this desk has published in three days. On Monday, Blackstone’s new data center REIT paid $5.0 billion for finished, Amazon-leased powered shells at a published 7.0 percent cap rate. On Tuesday, Fermi disclosed that an unnamed hyperscaler had prepaid about $200 million for power at a campus where no lease has been signed. Now Applied Digital has signed a lease for capacity that has not been built, with a tenant it has not named, for delivery that has not begun. Three different structures, one underlying question: who pays for the power, and who carries the tenant.
The arithmetic of higher pricing
The release says the lease “contains improved commercial terms over our prior leases, including higher pricing,” and the numbers let that claim be checked. Spread $5.4 billion over an 18-year base term and 150 megawatts, the new lease works out to about $2.0 million per megawatt per year. Those are arithmetic, not disclosures; the company published no per-megawatt rate. But the comparison with its own June deal is instructive. The June 8 lease at Delta Forge 2 covered 210 megawatts for 15 years at about $5.2 billion in base-term revenue — about $1.65 million per megawatt per year on the same arithmetic. The new lease prices roughly 21 percent higher per megawatt-year than the one signed five months earlier.
There is a second coincidence in the numbers worth noting. The June lease was also worth approximately $12.7 billion if all renewal options were exercised — the same headline total as the new lease, over a 30-year total term rather than 33. Same $12.7 billion, different shape: fewer megawatts, longer term, higher annual price. The renewal options add about $7.3 billion to each deal’s headline value — a reminder that the largest numbers in these announcements are the least certain ones. Renewal options are exercised 15 or 18 years from now, or they are not. The base term is the contract; everything beyond it is an option on a future the tenant has not committed to.
The book grew by exactly the size of the new lease. In June it stood at approximately $36 billion in base-term revenue, or $86 billion with renewals, across 1.4 gigawatts of critical IT load. Now it is more than $41 billion, or approximately $100 billion with renewals, across more than 1.6 gigawatts, and the investment-grade share has risen from about 70 percent to about 75 percent.
The tenant is unnamed, and that matters
The release does not name the tenant, and it does not name the campus. That silence is not unusual in this market — hyperscalers routinely insist on anonymity — but it changes what the $41 billion figure means. The credit quality is the landlord’s description, not a rating. Contrast the Blackstone deal from two days ago: there the tenant was Amazon Web Services, the rent was guaranteed by Amazon.com, and the transaction summary carried an AA rating from S&P on the parent. Here the tenant is “tier-one” and “investment-grade” in Applied Digital’s own words, and the market is asked to take the description on trust.
There is also an unanswered question about whether this is a new customer at all. The June release said the Delta Forge 2 lease was Applied Digital’s third long-term lease with the same U.S.-based investment-grade hyperscaler. The November release does not say whether this lease is a fourth with that tenant, or a first with a different one. The company’s fiscal first-quarter earnings release, issued in October, described the portfolio this way: Polaris Forge 1 is leased to CoreWeave, Polaris Forge 2 to an investment-grade hyperscaler, and Delta Forge 1, Polaris Forge 3, and Delta Forge 2 to a tier-one investment-grade hyperscaler. The new lease adds 150 megawatts to that picture without saying where it sits or whose name is on it.
That matters because concentration is the other side of the book’s growth. About 75 percent of contracted base-term revenue is now investment-grade, which means about a quarter of it is not. The non-investment-grade anchor is CoreWeave at Polaris Forge 1, and the Fermi piece two days ago laid out what has happened to neocloud credit this autumn: CoreWeave’s equity fell roughly 45 to 49 percent in four weeks in October, its 2031 senior notes traded at yields above 16 percent, and five-year credit default swaps on its debt widened past 1,240 basis points. A contracted-revenue book is only as strong as the tenants behind it, and a quarter of this one sits with a customer class whose financing model is under visible strain.
The power is not yet arranged
The most important sentence in the release may be the most easily skipped. “Delivery of the capacity is currently anticipated to begin in the first half of calendar 2028, subject to applicable development milestones, utility arrangements and regulatory approvals.” Delivery is more than a year away, and it is conditional. The release’s own forward-looking statements go further: they list among the risks “the satisfaction of conditions to effectiveness under our lease agreements, including the execution and regulatory approval of related power supply agreements.” Read plainly, that means the power supply agreements for this capacity have not yet been executed and approved — and that the lease’s effectiveness may depend on them.
This is the point where the three deals of the week diverge most sharply. The Blackstone portfolio is finished shells with live utility feeds; there is no energization risk left to underwrite. Fermi holds a Texas air permit covering about 6 gigawatts of on-site gas generation, turbines on site or on order, and a 200-megawatt utility connection. Applied Digital’s new lease is a signed contract for capacity whose power arrangements are, by the company’s own account, still to be completed. The lease is real paper. The power behind it is not yet real.
The portfolio figures carry their own quiet signal. More than 1.6 gigawatts of contracted critical IT load sits against 2.2 gigawatts of grid-connected peak load. The roughly 600-megawatt gap is the facility overhead — cooling, power conversion, and the other loads that keep a data center running on top of the computing equipment. Every megawatt of IT capacity a hyperscaler leases requires more than a megawatt from the grid, and the utility arrangements still to be completed must cover the full peak draw, not just the contracted IT figure.
How the build gets paid for
Chief financial officer Saidal Mohmand laid out the financing sequence in the release, and it is a deliberate order of operations. “We plan to finance this build through our established structure, including first-in equity already funded from our balance sheet and through our $5 billion programmatic equity partnership with Macquarie Asset Management, followed by project financing supported by the long-term lease with a tier-one investment-grade tenant.” Equity first — some of it already funded — then project debt, with the lease itself as the support for the borrowing.
The project finance timeline Mohmand gave covers the earlier campuses: completion of the remaining project finance for Delta Forge 1 and Polaris Forge 3 in the first calendar quarter of 2027, followed by Delta Forge 2 in the second calendar quarter of 2027. The new lease’s own project financing comes after the equity stages, and its timing was not stated. A second announcement the same day, reported by TipRanks and others, said the company had closed a $300 million senior secured bridge facility for Delta Forge 1, priced at SOFR plus 300 basis points — bridge money to carry construction while the longer-term project finance is arranged.
The sequence matters because it reveals what the lease is for. It is not only a revenue stream. It is the collateral that makes the project finance possible. Lenders underwrite a signed, long-term lease with an investment-grade tenant; the lease converts future rent into present construction capital. That is why the tenant’s credit description carries so much weight, and why the unnamed tenant is not a cosmetic detail. If the tenant’s credit were weaker, the project finance would be more expensive or smaller. The lease is a financial instrument before it is a building.
Three ways to slice the same risk
Put the week’s three deals side by side and the pattern is unmistakable. Blackstone bought finished buildings with a named tenant and a parent guarantee, and the market could price the result: 7.0 percent, $5.0 billion, 647 megawatts. Fermi took $200 million in cash from an unnamed hyperscaler before any lease exists, and the market priced the name when the Financial Times reported it was Amazon — up 60 percent in five sessions — even though the name changed nothing in the contract. Applied Digital signed a lease with an unnamed tenant for unbuilt capacity, and the market priced the headline: $41 billion of contracted revenue, shares up more than 20 percent.
Each structure moves a different risk to a different party. In the sale-leaseback, the construction and energization risk is gone, and what remains is tenant credit over 12 years, priced and guaranteed. In the prepayment, the hyperscaler carries the risk that a pre-revenue developer never delivers, in exchange for speed the grid cannot offer. In the Applied Digital lease, the developer carries the construction and power-arrangement risk for more than a year before delivery, the tenant carries an 18-year rent commitment, and the lenders who will fund the build in between carry the risk that the lease, the tenant, and the power all hold together until 2028.
None of these structures is wrong. All of them are responses to the same constraint: demand for AI computing capacity is arriving faster than the grid can serve it, and the money to build ahead of the grid has to come from somewhere. The question is not whether the structures work in principle. It is what each one is worth when the conditions attached to it are tested — when a lease’s effectiveness depends on power agreements not yet approved, when a prepayment’s refundability is undisclosed, when a cap rate set on finished buildings is applied to buildings not yet built.## What to watch
Four things will settle what the $41 billion book is actually worth. The first is the power supply agreements. The release’s own risk factors tie lease effectiveness to their execution and regulatory approval; until they are signed and approved, the lease is a contract whose conditions have not all been met. The second is the project finance calendar: Delta Forge 1 and Polaris Forge 3 in the first quarter of 2027, Delta Forge 2 in the second. Whether lenders price that debt the way equity priced the announcement will say more about the book’s value than Monday’s share price did.
The third is the tenant. If the tenant is ever named, or the campus identified, the market will be able to underwrite the credit for itself rather than taking the company’s description on trust. Until then, the investment-grade share of the book rests on Applied Digital’s characterization. The fourth is delivery itself. The first half of 2028 is the date the lease starts becoming revenue rather than contracted revenue, and it is more than a year of development milestones, utility arrangements, and regulatory approvals away.
Chairman and chief executive Wes Cummins said the lease “reinforces to us the strength of our customer relationships and the quality of our contracted revenue.” The relationships are real — this is at least the company’s fourth large hyperscaler lease in seven months. The quality of the revenue is a different claim, and it will be tested the way all such claims are tested: not on the day the lease is announced, but on the day the power is delivered, the rent starts flowing, and the project finance is repaid. The grid did not get bypassed this week. It got contracted — $41 billion of it, with the power arrangements still to come.