On October 6, 2026, Black Hills Corp. announced it had signed definitive agreements to serve a planned Google data center in Cheyenne, Wyoming — and put the most fully realized version of the bring-your-own-power model yet into a signed contract. The agreements, effective September 30, 2026, with terms running through 2048, include a Large Power Contract Services Agreement and a Generation Facilities Agreement. The headline number is 2.7 gigawatts. The more important number may be 22 years: a decades-long relationship in which the utility builds the gas plant, manages a private microgrid of third-party resources, and takes the load-growth business off the tariff sheet entirely.
Read the way Black Hills wrote it, the 2.7 GW figure is a total resource mix, including reserve margins, anticipated to serve the project — exclusive of additional transmission system expansion investments. It is not a disclosed Google IT load, and it is not Black Hills-owned plant. The project is planned to begin taking energy service in late 2027 and ramp to its peak load in 2030, but neither company has disclosed what that peak load is. The 2.7 GW is the size of the supply stack assembled to serve it, with reserves built in. Confusing the stack for the load is the first mistake this deal invites.
The two halves of the stack
The stack splits into two very different halves. Black Hills will provide up to 590 MW of grid-connected energy service through company-owned generation and market energy. Separately, it will manage the output of approximately 2.1 GW of Wyoming-based, third-party contracted resources through a privately managed microgrid, operating under the company’s Large Power Contract Service tariff. The first half is utility supply; the second is the utility as manager of someone else’s power, for a single customer.
The 590 MW grid-connected slice breaks down further. Black Hills will construct and own, through a non-regulated affiliate, 564 MW of new natural gas generation, nameplate capacity, at its existing Cheyenne Prairie Generating Station. The remaining 26 MW will come from market energy purchases and retail utility service under the company’s applicable industrial tariff. That ownership detail matters: the gas plant is company-owned, but it sits in a non-regulated affiliate rather than in the rate-based utility, which shapes how the investment earns its return.
The 2.1 GW half is the larger and the less described. These are third-party contracted resources, located in Wyoming, whose output Black Hills will manage rather than own. The company has not disclosed who the third parties are, what technologies the resources use, or how the 2.1 GW divides among them. What is disclosed is the service Black Hills sells around it — coordinating grid operations, reliability services, and energy dispatch — and the fee it earns for doing so.
The money
To support the project, Black Hills plans to invest $1.8 billion between 2027 and 2029 to construct the 564 MW of company-owned generation. Black Hills expects to begin earning a return on that investment when construction begins in 2027, and the project to provide approximately $150 million of net income in 2030. Beyond 2030, Black Hills will continue to earn microgrid management fees and a return on its capital investment, with the generation fully depreciated by 2048. The project is expected to deliver approximately $2.4 billion of unlevered free cash flow through 2048, net of the $1.8 billion of capital investment.
Those figures are Black Hills’ expectations, stated in a filing that carries the standard forward-looking-statements caution: timing, scope, and benefits depend on regulatory approvals, counterparties performing, and construction going to plan. They are also easy to misread. The $1.8 billion is Black Hills’ capital expenditure, not Google’s contracted revenue and not the value of the deal. The $150 million is expected net income in a single year, 2030, the year the project reaches peak load — not an annual run rate from day one. And the $2.4 billion is a through-2048 cumulative figure, net of the capital spend. None of them is the price Google is paying for power.
One more number deserves the same care. Google has provided Black Hills with $399 million of refundable advances for the procurement of long lead-time equipment under the parties’ generation reservation agreement, and Black Hills expects to reimburse those advances by June 30, 2027. A refundable advance is not a payment for power, not an investment in the plant, and not the deal value. It is working capital — Google fronting cash so turbines and long-lead components can be ordered before construction begins, with the money coming back within months.
The utility as power developer
This deal is the natural extension of the bring-your-own-power story this desk laid out in October — and it changes the protagonist. In that explainer, the data center operator was the one weighing turbines, fuel cells, and small modular reactors at the fence, learning to think like a power developer because the grid could not deliver on its timeline. In Cheyenne, the operator is not building the plant. The utility is. Google’s role is to sign a 22-year contract, advance equipment money, and bear the costs. Black Hills’ role is to build 564 MW of gas generation, contract and manage 2.1 GW of third-party resources, and stand behind the arrangement through 2048.
That inversion is the point. The bring-your-own-power model began as operators routing around utilities that could not move fast enough. Cheyenne shows a utility moving fast enough to keep the business — by becoming the developer, the owner, and the manager itself. The customer gets power on a timeline the interconnection queue could not offer: service beginning in late 2027. The utility gets a contracted, decades-long load with cost recovery locked in. The grid’s planning problem is handled inside a single negotiated contract.
The microgrid management fee is the newest piece of the model, and it deserves attention as a business line rather than a footnote. Black Hills will receive fee revenue for coordinating the portfolio, at a negotiated rate based on a contracted minimum peak load expected to begin in 2027 and rise through the ramp period, with revenue anticipated to begin in late 2027. This is not volumetric energy sales. It is a fee for operating a private power system — dispatch, reliability, coordination — priced off a contracted minimum load. If the model spreads, managing other parties’ resources for large customers could become a distinct utility service.
The protections, and who pays
The most politically important sentences in Black Hills’ announcement are about who does not pay. The agreements and supporting regulatory mechanisms are structured so that Google bears all costs associated with serving the planned data center throughout the life of the project, president and CEO Linn Evans said the agreements demonstrate how innovative energy solutions can support economic growth “while ensuring existing customers are protected.” The structure includes cost pass-through mechanisms, stranded-asset protection with full recovery of all generation capital investment over the contract term, early termination protection, and credit protections, with collateral and financial assurance backing the data center’s long-term commitments.
That package is doing the same work TVA’s new data center tariff does, by a different mechanism. TVA, as this desk covered in October, prices the reservation itself — roughly $1.5 million per megawatt above five megawatts — so that speculative load pays upfront for the capacity it reserves. Black Hills and Wyoming have instead written the protections into a negotiated contract: the single customer bears all costs, the capital is fully recoverable over the term, and collateral stands behind the commitment. Both answer the same question — who pays when a gigawatt-scale load arrives on a system built for ordinary customers — but in opposite registers. TVA’s is a tariff, published and general. Cheyenne’s is a contract, negotiated and specific.
The regulatory groundwork is already substantially laid. The Robinson substation certificate of public convenience and necessity was approved in May 2026. An industrial siting permit for the Cheyenne Prairie expansion was filed in July 2026, and an air quality permit for the expansion was approved in August 2026. On transmission, a Large Customer Transmission Cost Adjustment Mechanism was filed in June 2026, a South Cheyenne Transmission Expansion certificate was filed in September 2026, and a Wyoming transmission expansion certificate is to be filed in the fourth quarter of 2026. The 2.7 GW figure excludes additional transmission investments, which Black Hills is advancing for this project and other regional large-load opportunities.
What this means for the load-growth business
Step back, and Cheyenne looks like a migration. The load-growth business is moving from tariffs to bespoke, decades-long contracts. A tariff is a published price for a standard service; it works when customers are interchangeable. A hyperscale data center is not interchangeable — its load is larger than many utilities’ entire systems, its timeline is measured in months, and its credit is strong enough to collateralize a 22-year commitment. Black Hills’ answer is to negotiate rather than publish. The package is a services agreement, a generation facilities agreement, a reservation agreement for equipment, a management fee tied to a contracted minimum peak load, and a regulatory mechanism for transmission costs. The contract, not the rate schedule, is the product.
That migration carries a tradeoff regulators and other customers should watch. Bespoke contracts can protect existing customers more precisely than a general tariff — every cost assigned, every risk collateralized, every termination priced. But they are also opaque. The price Google pays for power is not disclosed. The identities and technologies of the 2.1 GW of third-party resources are not disclosed. The microgrid management fee is a negotiated rate, not published. A tariff’s virtue is that everyone can see it; a contract’s virtue is that it can be tailored. Black Hills serves 1.37 million customers across eight states, so a project expected to contribute roughly $150 million of net income in 2030 is material to a company of that size.
The gas question
One tension the announcement does not resolve is the fuel. The company-owned generation at the heart of the deal is 564 MW of new natural gas, and gas is what makes the late-2027 timeline achievable — turbines can be ordered, permitted, and built on a schedule no other firm resource can match at that scale. It is also what makes the deal sit uneasily with the climate commitments hyperscale operators have published, Google included. Black Hills’ release does not describe how the gas generation squares with Google’s emissions goals, or whether the third-party resources include renewables or storage. None of that is disclosed, and none of it should be assumed.
The composition of the 2.1 GW is the largest open question in the deal. If a meaningful share is wind, solar, or storage — Wyoming has abundant wind — the portfolio changes from a gas story to a hybrid one, and the microgrid management task becomes genuinely complex: dispatching variable third-party resources against a flat, around-the-clock load, with 590 MW of gas and market energy as the firming layer. If it is mostly gas, the story is simpler and the emissions profile heavier. Until Black Hills or Google says more, the honest description is the one the filing gives: approximately 2.1 GW of Wyoming-based, third-party contracted resources.
What to watch
Four things will determine whether Cheyenne becomes a template or a one-off. The first is construction: whether the 564 MW at Cheyenne Prairie breaks ground in 2027 as planned, whether the long-lead equipment arrives on schedule, and whether the $1.8 billion stays $1.8 billion. Gas turbine supply chains are tight. The second is transmission. The South Cheyenne expansion certificate was filed in September 2026, and a broader Wyoming transmission expansion certificate is due in the fourth quarter of 2026. Transmission is the part of the project excluded from the 2.7 GW figure, and the part most likely to draw scrutiny over cost and over who benefits from lines built for one customer.
The third is disclosure around the 2.1 GW. The identities, technologies, and contract terms of the third-party resources will shape how the industry reads this deal — as a gas project with a microgrid wrapper, or as a genuinely hybrid portfolio a utility can assemble and operate for a customer. The fourth is imitation. If Cheyenne works — service in late 2027, ramp to peak load in 2030, earnings contributing from 2027, no cost shift to existing customers — expect other small and mid-size utilities to study the structure closely: the non-regulated affiliate for generation, the negotiated management fee, the reservation agreement with refundable advances, the contract-level customer protections. Whether regulators in other states accept it is another question.
The boundary this desk has tracked all autumn — between electricity customer and electricity supplier — has now blurred from the other direction. It is no longer only data center operators learning to think like power developers. In Cheyenne, the utility has learned to think like a developer, an owner, and a microgrid operator, all for a single customer, under a single 22-year contract. The grid did not get bypassed. It got hired — to build the plant and manage the portfolio, for a fee, through 2048.