On September 30, 2026, a 33-megawatt power block in Beaver County, Utah, began selling electricity. Four weeks earlier, Google had agreed to buy 396 megawatts from the project it belongs to. Together they put a new entrant into the data center power story: geothermal energy, enhanced by shale-industry drilling, has moved from pilots into commercial operation — and into a contract book of about 1.1 gigawatts tied to American data centers.
The developer is Fervo Energy, the Houston geothermal company behind Cape Station. The first GeoBlock — Fervo’s term for a standardized unit of geothermal generation — synchronized to the grid on September 24 and declared commercial operation on September 30, a day ahead of its contractual deadline.
What Google actually signed
Precision matters, because the deal has two very different halves. On September 1, Fervo and Google announced a 396-megawatt power purchase agreement for electricity from Cape Station, which Fervo describes as the largest enhanced geothermal PPA signed to date. The contract is a 15-year, grid-connected, take-or-pay agreement: Google pays for the power on fixed terms for the life of the contract, whether or not the Utah data center the power is meant to serve gets built. The 396 megawatts will be delivered in four tranches of 99 megawatts each, with first power expected in mid-2028 and the full set of GeoBlocks targeted to be online before the end of 2028.
The second half is an option. Fervo has committed to offer Google the chance to expand its offtake by approximately 600 megawatts, for a total of nearly one gigawatt, with a decision due by June 2030. That expansion is tied to a proposed Google data center in Utah, whose final plans Fervo cautions remain subject to engineering feasibility, state and local approvals, and commercial conditions. The 396 megawatts are binding. The 600 megawatts are not. Treating the two as one deal would overstate what has actually been committed by roughly half.
The structure of the binding contract also matters. It is a grid-connected deal, not a behind-the-meter one: Fervo builds on its own timeline and delivers power into the grid, while Google develops its data center infrastructure independently. The option, however, is where the fence-line version may emerge: for the additional 600 megawatts, Fervo and Google are pursuing direct, behind-the-meter supply to the data center under Utah’s SB132, subject to regulatory approval. The grid PPA is the present; the direct connection is the test case.
Cape Station, by the numbers
Phase I comprises approximately 100 megawatts across three 33-megawatt GeoBlocks. The first reached commercial operation on September 30. The second had synchronized to the grid by early November. Fervo expects both remaining blocks to reach commercial operation by January 1, 2027, completing Phase I.
The company’s third-quarter results put 36 megawatts in operation across Cape Station and its earlier Nevada pilot, Project Red, with another 66 megawatts in GeoBlocks 2 and 3 in commissioning and 400 megawatts in GeoBlocks 4 through 11 under construction. That 400-megawatt block is now called Cape Google 400: eight GeoBlocks built to deliver the Google contract, a $2.2 billion investment through 2028. A third-quarter resource study estimated 8.4 gigawatts of capacity potential at Cape Station, nearly double the prior estimate of 4.3 gigawatts. Whether the deeper resource can be developed at the costs Fervo projects is the question that will decide how much of that 8.4 gigawatts is real.
How the technology works — and why it took this long
Enhanced geothermal systems, or EGS, solve the oldest problem in geothermal power: good heat is common underground, but naturally permeable rock with enough water is rare. Conventional geothermal plants, which supply most of the roughly 4 gigawatts of U.S. geothermal capacity, sit on natural steam fields, more than nine-tenths of them in California and Nevada. EGS creates the reservoir instead of finding one. Fervo drills pairs of horizontal wells into hot granite, stimulates fractures between them with high-pressure water, and circulates fluid from one well to the other. The hot water returns to the surface and drives binary turbines before being reinjected.
The technique is borrowed wholesale from the shale industry, and that borrowing is both the promise and the risk. The promise is repeatability; the risk is that the subsurface is less predictable than a factory floor. A fractured reservoir can underperform, lose water, or cool faster than modeled, and each of those failures is expensive to diagnose and fix thousands of feet down.
That history is why September 30 matters more than September 1. Contracts are cheap; commercial operation is not. The U.S. geothermal fleet produced about 16 billion kilowatt-hours in 2025, roughly 0.4 percent of utility-scale generation, a share that has barely moved since 2001. Fervo booked just $116,000 in third-quarter revenue, a single day of commercial operation.
The 1.1-gigawatt tally
Google’s Utah deal does not stand alone. Counting contracts signed for U.S. data centers, the total now comes to about 1,149 megawatts, according to a tally by AIxEnergy, a research publication that tracks the deals. Google holds nearly three-fifths — 666 megawatts — with most of the rest due between 2027 and 2030.
The Nevada deals form the second leg. Google’s 115-megawatt contract with Fervo, approved by the Public Utilities Commission of Nevada in May 2025 under the state’s Clean Transition Tariff, pairs with a February 2026 Ormat Technologies portfolio PPA of up to 150 megawatts, also through NV Energy’s tariff, with projects expected online from 2028 to 2030. The Nevada commission has yet to approve the Ormat portfolio; a ruling is expected around the end of 2026 or early 2027. Meta has signed two deals of up to 150 megawatts each: one with Sage Geosystems in Texas, announced in August 2024 with a first phase targeted for 2027, and one with XGS Energy in New Mexico, projected to be fully operational by 2030. Amazon is backing a 20-year contract under which Zanskar is to supply NV Energy with 100 megawatts from new Nevada plants by 2030, to serve Amazon’s data centers near Reno; that contract still needs the Nevada commission to approve the utility’s 2026 resource plan. Switch has contracted about 13 megawatts from Ormat’s Salt Wells plant in Nevada for delivery from 2030. Older deals in the tally include about 32 megawatts Switch has drawn from Ormat’s Don A. Campbell plants since 2019, and 38 megawatts of behind-the-meter geothermal for defense computing.
One caution belongs on the tally: it counts “up to” figures and contracts still awaiting regulatory approval, so the firm, fully permitted total is smaller than 1,149 megawatts — a snapshot of commitments, not a forecast.
What geothermal does that gas and nuclear do not
The bring-your-own-power explainer on this desk laid out the options a month ago: gas turbines as the near-term workhorse, small modular reactors as the long-term bet, fuel cells as the middle path. Geothermal was not in the frame. It belongs there now, because it occupies a position none of the others holds: firm, carbon-free power with no fuel cost and no air emissions, from a technology that is operating commercially today rather than awaiting a first deployment.
Against gas, the contrast is straightforward. A gas turbine is cheaper to build and faster to deploy, but it burns fuel, emits carbon dioxide and nitrogen oxides, and exposes the operator to commodity prices for decades. Against nuclear, the contrast is timeline: no SMR design has yet been deployed commercially at a U.S. data center, and licensing stretches toward a decade, while Cape Station went from construction to commercial operation in roughly two years for its first block. Against solar and wind, the contrast is intermittency: a geothermal plant runs around the clock, which is what a data center needs.
But geothermal’s advantages come with constraints the other options do not face. The first is geography. Gas turbines and SMRs can be sited almost anywhere; geothermal needs hot rock at drillable depth, which concentrates the resource in the Great Basin of Nevada and western Utah and a scattering of other basins. A data center that wants geothermal power either builds near the resource or buys it over the grid, and the grid option reintroduces the interconnection and transmission questions that bring-your-own-power was meant to escape. The second is geology risk: a gas plant’s output is a function of equipment and fuel, both knowable in advance, while a geothermal reservoir’s performance is proven only by drilling into it. The third is water: Fervo’s Nevada pilot reported losing about 30 percent of the water it injected underground, and in the arid Great Basin, water use is a permitting and community issue that will follow every project. Enhanced systems also carry the risk of induced seismicity, which operators manage under mitigation protocols.
The cost question
The decisive question for geothermal is cost, and Fervo has now put numbers on the record. The company expects its first phase to come in at about $7,000 per kilowatt, has set a cost target of $5,500 per kilowatt for the 400-megawatt second phase, and holds a longer-term target of $3,000 per kilowatt. Set those figures against the alternatives this desk has priced: recent U.S. combined-cycle gas plants have come in at roughly $2,293 to $2,500 per kilowatt installed, according to the Institute for Energy Economics and Financial Analysis. Geothermal at $5,500 per kilowatt is more than twice the installed cost of a new gas plant — the comparison is not exact, since a geothermal plant has no fuel cost, but it explains why geothermal needs either a buyer willing to pay a premium for carbon-free firm power or a cost decline toward the $3,000 target. The financing structure is doing some of the work. Nevada’s Clean Transition Tariff, under which the Fervo and Ormat deals are structured, lets Google pay the difference between the geothermal price and the cheaper resource NV Energy would otherwise build, so the utility can sign for first-of-a-kind capacity without passing the premium to other customers. The Google PPA in Utah is a take-or-pay contract with fixed terms, which gives Fervo the revenue certainty to finance construction.
The Utah campus and the behind-the-meter test
The most consequential open question is not the 396 megawatts but the 600. If Google exercises its option and the behind-the-meter structure under Utah’s SB132 goes ahead, the result would be the first large-scale test of whether a hyperscaler will build a data center at a remote Great Basin site — limited water, limited fiber — in order to sit next to its power source. A 2025 Rhodium Group study estimated that if data centers keep clustering where they historically have, behind-the-meter enhanced geothermal could economically serve 55 to 64 percent of projected hyperscale demand growth by the early 2030s, or 15 to 17 gigawatts. Signed contracts amount to about 7 percent of that midpoint.
Those are modeled estimates, not commitments, and they assume faster permitting than the system currently delivers. About 65 percent of U.S. geothermal capacity sits on federal land, where the Bureau of Land Management took an average of 455 days to bring a nomination to auction, according to the Government Accountability Office. There is also a concentration risk that the tally makes plain. Because one buyer holds most of the contracted U.S. capacity, a change in Google’s plans would reshape the sector’s order book. The take-or-pay structure of the Utah contract insulates Fervo for the 396 megawatts, but the option and the resource’s 8.4-gigawatt potential depend on Google — and on Meta, Amazon, and the others — continuing to buy.
Niche or foothold?
So is 1.1 gigawatts a niche or a foothold? On the niche side: the entire U.S. geothermal fleet is about 4 gigawatts, the contracted data center total is barely a quarter of that, and nearly all of it is due in a three-year window that depends on drilling results, permits, and regulatory approvals that have not yet arrived. Geothermal’s share of AI load growth will remain a minority through the early 2030s at current build rates. On the foothold side: a commercial plant is operating and generating revenue, a binding contract book exceeds a gigawatt, a hyperscaler has committed to fixed-price, take-or-pay terms for fifteen years, and tax credits are preserved through 2033. Gas is faster and cheaper but carries emissions and fuel risk. Nuclear is cleaner and firmer but years from deployment. Geothermal is the only option that is firm, carbon-free, and already running.
What decides it: Phase I completion by January 1, 2027; the Nevada commission’s ruling on the Ormat portfolio; whether Phase II lands near $5,500 per kilowatt, giving lenders a reference project for enhanced geothermal; and Google’s option, open until June 2030. Geothermal has joined the bring-your-own-power conversation not as a theory but as a plant that is selling electricity and a contract book that exceeds a gigawatt. It is the smallest entry in the playbook by capacity and the most geographically constrained. Whether that combination earns it a larger share of the next wave of data center power depends on drilling results, costs, and a Utah campus that has not yet been approved.