Two announcements, seventeen days apart, say more about the AI power build-out than any headline gigawatt total. On November 10, Fermi Inc. announced that an unnamed investment-grade hyperscaler would prepay about $200 million to advance 600 megawatts of power at its private-grid campus near Amarillo, Texas — and in its own words, the deal is a non-binding letter of intent. Fermi’s quarterly filing states that it has “not entered into definitive lease agreements with any tenants.” On September 30, six weeks earlier, the first 33-megawatt block of Fervo Energy’s Cape Station geothermal plant in Utah entered commercial operation, a day ahead of its contractual deadline, delivering under a 15-year take-or-pay contract with Google for 396 megawatts — the kind of contract lenders write checks against.

Both get filed under “AI power deal.” They are not the same thing, and the gap between them is where the sector’s risk now sits. That is the argument of a November 25 analysis from SEQH Capital Research, which graded its tracker of 22.5 gigawatts of agreements signed by Amazon, Meta, Google and Microsoft the way a lender would: is it signed, is it financed, is it licensed — and when does the power actually show up?

The 22.5 gigawatts, in five kinds of deal

The largest bucket, 9.6 gigawatts or 43 percent, is output from plants already running: long-term contracts for power from existing nuclear plants. Meta’s 2,176 megawatts from Vistra’s Perry and Davis-Besse plants in Ohio, Google’s 2,700-megawatt, 15-year agreement across Constellation’s PJM fleet, and Amazon’s 1,920 megawatts from Talen’s Susquehanna plant in Pennsylvania anchor it. The second bucket, 9.5 gigawatts or 42 percent, is new reactors: Amazon’s backing for 5 gigawatts of X-energy small modular reactors, Meta’s agreements with TerraPower and Oklo, and Google’s 500 megawatts from Kairos Power. Then the small stuff in the middle: 1.5 gigawatts of restarts, 1.5 gigawatts of uprates, and 0.4 gigawatts of geothermal — the only new supply in the tracker with any plausible path to the grid this decade.

The arithmetic is worth sitting with before the detail. Of the 22.5 gigawatts, 9.6 add no new electrons at all. Of the 12.9 that are nominally new, 9.5 are reactors that do not exist and none of which arrives before 2030. That leaves 3.4 gigawatts of restarts, uprates and geothermal — and of that, only about 1.8 gigawatts, the two restarts plus Fervo, has a dated path to the grid before 2030. Eight percent of the headline number.

The biggest bucket adds no power

Start with the 9.6 gigawatts, because it is the part of the tracker that is most real and most misunderstood. These are genuine, signed, long-term contracts with investment-grade buyers, and for the plant owners they are transformative: 15- to 20-year agreements turn merchant nuclear plants into something closer to infrastructure, with the revenue certainty to fund equipment upgrades and pursue license renewals. Vistra’s deal with Meta, announced January 9, covers 2,176 megawatts of operating capacity at Perry and Davis-Besse plus 433 megawatts of uprates, with purchases beginning in late 2026 and the full 2,609 megawatts online by 2034.

But a contract on existing output does not add supply, and in a market where data center load is the marginal demand, that distinction is the whole story. Google’s 2,700 megawatts is a financial energy agreement covering Constellation’s existing PJM fleet — the plants keep running and keep selling into PJM, as Constellation’s own announcement puts it, “without taking resources off of the grid.” Amazon’s Susquehanna deal ramps up and does not reach its full 1,920 megawatts until 2032. The power is real, the contracts are binding, and the grid has exactly the same number of megawatts it had before the deals were signed.

This is the additionality question this desk laid out in its explainer on data center power deals, now with a number attached. A PPA with a new-build wind farm is the gold standard because the contracted revenue directly enables financing. A contract for the output of a plant that has been running for decades keeps it alive and its output contracted, which is valuable — but it does not build a megawatt. When the tracker is quoted as 22.5 gigawatts of “AI power,” nearly half of it is supply secured, not supply created.

The new reactors: 9.5 gigawatts, none before 2030

The second bucket is the largest pile of nominally new capacity, and the furthest from delivering a kilowatt-hour. None of the four deals in it arrives before 2030, and none is a firm order for a reactor in the sense a lender would recognize. What the buyers hold is mostly an option on future output, and the developers carry the cost, licensing and schedule risk until a plant runs.

Amazon’s 5 gigawatts with X-energy is the biggest of the four and the least concrete. X-energy’s IPO prospectus describes “options” to bring more than 5 gigawatts online by 2039. The first project, with Energy Northwest in Washington, is four Xe-100 reactors totaling 320 megawatts, expandable to 960 megawatts; its permit status is not stated in the prospectus. Meta’s TerraPower agreement funds early development of two Natrium units capable of generating up to 690 megawatts, with first power “as early as 2032,” and gives Meta rights to energy from up to six more targeted for delivery by 2035. No site has been chosen. TerraPower’s own Kemmerer reactor in Wyoming — which has nothing to do with Meta — received its construction permit in March and broke ground in April, and is still years from operation.

Meta’s Oklo agreement is for a new nuclear campus in Pike County, Ohio, of up to 1.2 gigawatts, with first power “as early as 2030”; funding terms are not disclosed. Google’s Kairos deal, for 500 megawatts by 2035, is the furthest along of the four: Hermes 2, a 50-megawatt plant for Google via the Tennessee Valley Authority, broke ground in April, with operations expected by 2030. That is a construction permit in hand and steel in the ground — and still a 50-megawatt demonstration whose first power is four years away.

None of this means these reactors will not be built. It means the headline gigawatt figure prices an option as if it were power. A construction permit, a final investment decision or a binding PPA on any of these deals — especially the first Energy Northwest units for Amazon — would change the grade.

The middle: restarts and uprates

The supply that can actually arrive sooner is the small stuff in the middle, and the most advanced work in the tracker. Microsoft’s Crane Clean Energy Center, the former Three Mile Island Unit 1, is an 835-megawatt restart backed by a 20-year PPA. The Energy Department closed a $1 billion loan for the project in November 2025, the NRC has approved on-site storage of new fuel while it reviews the restart, and FERC granted a waiver easing reconnection to the grid. Constellation targets 2027. What is left is the NRC’s final approval to restart.

Google’s Duane Arnold restart in Iowa is the second. NextEra holds a 25-year PPA with Google for the 615-megawatt plant, which shut down in 2020 after a derecho damaged a facility already slated for retirement. The Energy Department closed a loan of up to $1.9 billion for the restart on September 8, 2026, and NextEra targets the first quarter of 2029. The NRC issued a draft environmental assessment in August. Contracted and financed, like Crane, with the NRC as the remaining gate.

The uprates are the next tier down in certainty. Google’s deal with Constellation, announced October 6, funds 890 megawatts of uprates across 11 nuclear units, with more than $4.3 billion of investment and the first uprate expected in 2028. Amazon’s 20-year Calvert Cliffs agreement covers 690 megawatts including a 190-megawatt uprate due between 2030 and 2032. Meta’s Vistra deal adds 433 megawatts of uprates, with capacity added through 2034. Each uprate needs NRC approval, and the financing is conditional: the Energy Department offered up to $5 billion for Constellation’s uprates on October 27 and up to $4.2 billion for Vistra’s on October 5. Conditional means the money is not committed until the borrowers satisfy technical, legal, environmental and financial conditions.

Geothermal, the exception that proves the rule

That leaves the smallest bucket, and the one this desk covered in detail a week ago: Google’s 396 megawatts from Fervo Energy’s Cape Station. It is 2 percent of the tracker and the only entry that is firm, carbon-free and already running. The first 33-megawatt GeoBlock synchronized to the grid on September 24 and declared commercial operation on September 30, under the 15-year take-or-pay contract. The 396 megawatts arrive in four 99-megawatt tranches, with first power expected in mid-2028 and full delivery before the end of 2028.

Fervo’s position in the grading is the instructive contrast. It is signed, it is operating, and its first block beat its deadline — but the larger build is not yet financed. Phase I closed $421 million of non-recourse debt in March; Phase II, a roughly $2.2 billion build through 2028, has no project debt announced yet. SEQH reports drilling is about 18 percent complete and the first turbine set has passed factory testing. The test that matters now is whether lenders will back geothermal at scale.

The money: $12.1 billion offered, $2.9 billion closed

The financing picture tells the same story as the capacity picture, in dollars. Four Energy Department loan commitments sit behind these deals, totaling up to $12.1 billion: $1 billion for Crane, $1.9 billion for Duane Arnold, $5 billion for Constellation’s uprates and $4.2 billion for Vistra’s. Of that, $2.9 billion has closed — all of it for the two restarts. The $9.2 billion for uprates is still conditional, and the new-reactor deals carry no federal loan commitments at all in the tracker.

That split is the most important number in the analysis after the 1.8 gigawatts. The federal government has put real, closed money behind the cheapest and fastest new megawatts in the country — restarting plants that already exist — and conditional money behind squeezing more out of plants that already run. It has put nothing behind the 9.5 gigawatts of new reactors, because those are not yet financeable in the form they currently take.

What it means for the developers counting on it

For a data center developer, the implication is blunt. Before 2030, the load that hyperscalers are building runs on gas and the grid. That is why Fermi’s campus is built around gas turbines, with nuclear as a 2034-and-later plan, and why its filings describe a pre-revenue developer racing a December 31 clock — a mandatory prepayment under its Keystone loan facility and a notice to proceed from the Texas Tech University System, both conditioned on a lease that does not yet exist.

The same logic runs through the rest of the sector. Interconnection queues stretch three to seven years where major upgrades are needed. The 22.5-gigawatt tracker looks like an answer to that queue, but 9.6 gigawatts of it is power that was already on the grid, 9.5 gigawatts of it is power that cannot arrive before 2030, and the dated new supply before 2030 is 1.8 gigawatts plus the first uprates from 2028. A developer that plans a campus around a headline gigawatt figure is planning around a number that was never a delivery schedule.

There is a second, quieter implication for the grid. The 9.6 gigawatts of existing-output contracts do real work: they keep plants running that were slated for early retirement — Davis-Besse and Perry were both headed that way a few years ago — and they fund uprates and license renewals. That is a genuine contribution to reliability. It is not, however, new supply, and it should not be counted as such in any planning exercise that asks how much generation the AI build-out still needs.

What to watch

Five things will settle whether the tracker is a pipeline or a press release. The first is Crane’s NRC restart approval — the first new nuclear electrons in the tracker, and a test of how fast restarts can move. The second is whether the Energy Department closes the conditional loans for Constellation’s $5 billion and Vistra’s $4.2 billion. The third is a firm order behind an option: a construction permit, a final investment decision or a binding PPA on any of the new-reactor deals, especially the first Energy Northwest units for Amazon. The fourth is Phase II financing at Cape Station. The fifth is Fermi’s lease — whether the 600-megawatt letter of intent becomes a lease by December 31.

The headline number will keep growing, and the press releases will keep using the same words for all of them. The useful question is the one SEQH asked: signed what? A take-or-pay PPA with a hyperscaler can be financed. A letter of intent, an option or a framework agreement cannot. Of 22.5 gigawatts of AI power deals, 1.8 gigawatts is new supply with a date. Signed isn’t built — and for the next four years, the difference is the story.