Two weeks after the Tennessee Valley Authority signed its first agreement under its new data center tariff, the deal has acquired something it did not have on the day it was disclosed: confirmation. TVA spokesperson Scott Brooks told Knoxville television station WVLT that the arithmetic this desk and others did on the filing — $1.7 billion in aggregate payments at roughly $1.5 million per megawatt of requested capacity above five megawatts, implying a load on the order of 1,100 megawatts — checked out. He did not confirm the capacity, and TVA still has not named the customer or the site.

This desk reported the deal itself on November 14: the agreement signed November 10, 2026, disclosed in TVA’s fiscal 2026 annual report, entitling TVA to $1.7 billion in aggregate payments, with $31 million due on signing and the balance paid over 59 subsequent installments. The news then was that anyone would sign under a $1.5 million-per-megawatt reservation price. The news now is what the signature actually buys. A tariff is a design, and designs are judged by how they allocate risk, not by how large the first number is.

The design TVA chose is now one of three working answers to the same question. Oregon’s Pacific Power tariff, approved November 13, prices the cost a data center causes into a negotiated contract. Black Hills’ Cheyenne deal with Google, signed in October, skips the tariff entirely and writes the protections into a bespoke 22-year contract. TVA’s answer is the published, general one: a rate schedule, set by the board of the nation’s largest public power supplier, that any large load can read before it signs. All three attack the same phantom-load problem — a customer reserving capacity it may never use, leaving everyone else to pay for the build.

What $1.5 million per megawatt actually buys

The $1.7 billion is not the price of power. It is not annual revenue. It is aggregate payments under a Capacity Commitment Charge agreement — a charge for reserving capacity, layered on top of the ordinary rate the customer will pay for the electricity it actually consumes. TVA moved data center load into its own rate class in August, with average billing rising approximately 10 percent phased in over three fiscal years. The customer pays to reserve the capacity, then pays again to use it.

What the reservation buys, in TVA’s framing, is the incremental capacity cost the data center rate does not cover. CFO Tom Rice — since promoted to president, with Mike Skaggs retained as CEO — has said the provision covers what the rate alone misses: the generation, transmission, and substation capacity the new load requires. In a developer’s siting model it is a line item: a 100-megawatt request carries roughly $142 million in commitment charges on the 95 megawatts above the threshold. A gigawatt-scale request carries a bill in the low billions before a single server is powered.

It is worth asking what that money does not buy. It does not buy faster interconnection: engineering studies, upgrade timelines, and the physical constraints of the grid remain what they were. Nor a fixed price for the next customer: TVA’s filing says the $1.5 million rate “reflects TVA’s current cohort-based pricing methodology, which may be revised for future customer cohorts.” And it does not buy certainty about the cost of serving this load. “Incremental capacity cost” is an estimate made before the generation and transmission are built; the true cost will only be known when the assets are in service.

Three templates for the same question

The comparison that matters most is with Oregon, because Oregon’s answer is the toughest tariff a state commission has yet approved — and it works almost the opposite way. Pacific Power’s Schedule 401, approved November 13 in Order No. 26-443, applies to facilities using 20 megawatts or more, and it is direct contracting, not a stated class rate: each large facility negotiates its own commission-reviewed agreement, lasting 10 to 30 years, priced around the generation, storage, and wires built to serve it, and market power bought before new generation comes online. New resources serving these facilities must be non-emitting, and facilities of 100 megawatts or more pay an additional 1 cent per kilowatt-hour into a fund for low-income customers.

Oregon’s design has a feature TVA’s lacks. Pacific Power, commission staff, the Citizens’ Utility Board — Oregon’s statutory ratepayer advocate — and environmental intervenors signed a joint stipulation on September 16 resolving every disputed issue, and the commission ratified what the adversaries had already negotiated. The Citizens’ Utility Board called it “the strongest from a for-profit electric utility yet” under the POWER Act. A formula with the ratepayer advocate’s signature on it is a much harder thing to unwind than a formula a utility wrote alone. TVA’s tariff has no such settlement: it was adopted by TVA’s own board, which sets its own wholesale rates as a federal power producer, with no state commission, no ratepayer advocate, and no intervenors at the table. That is also its strength — no regulator had to be persuaded, and no appeal to a state court can stall it. But the durability Oregon bought through negotiation, TVA must buy through results.

Cheyenne is the third template, and the furthest from a tariff. Black Hills signed definitive agreements in October to serve a planned Google data center in Wyoming: a 2.7-gigawatt resource stack, 22-year terms running through 2048, in which the utility builds 564 megawatts of gas generation at its Cheyenne Prairie station through a non-regulated affiliate and manages roughly 2.1 gigawatts of third-party resources through a privately managed microgrid. The protections are contractual: Google bears all costs of serving the project, generation capital is fully recoverable over the contract term, early termination is priced, and collateral stands behind the commitment. Google fronted $399 million in refundable advances for long-lead equipment, which Black Hills expects to reimburse by June 30, 2027.

Put the three side by side and the trade-off is plain. TVA’s tariff is transparent — anyone can read the $1.5 million rate — but general: the same price for every customer in the cohort, with the terms of any single agreement largely undisclosed. Oregon’s tariff is transparent about the rules and opaque about the price, since each facility negotiates its own contract. Cheyenne is opaque about both — the price Google pays for power is not disclosed, nor are the identities of the third-party resources — but precise about the protections, because every cost and every risk is assigned in a single negotiated document. A tariff’s virtue is that everyone can see it. A contract’s virtue is that it can be tailored.

Who bears the risk if the load never arrives

The question that will decide whether TVA’s design works is the one the filing does not answer: what happens if the customer delays, downsizes, or walks away? The $31 million due on signing is real money, and 59 installments behind it are a real commitment. But the disclosure gives no termination terms, no downsizing provisions, no milestones, no energization date — and no term in years, only a 60-payment schedule. The public cannot yet judge the counterparty risk: whether this is a hyperscaler for whom 60 installments are a formality, or a developer whose ability to pay depends on financing not yet closed. Until the load is energized and consuming power under the Large Data Service schedules, the $1.7 billion is a payment stream, not a served customer.

The contrast with the other two templates is sharp. In Oregon, the facility signs its service contract and commits to the cost before the utility builds anything, for 10 to 30 years, with the commission reviewing the agreement. In Cheyenne, collateral and financial assurance back the commitment, the generation capital is fully recoverable over the term, and the customer has already advanced $399 million in cash for equipment. TVA’s structure has the $31 million and the installments — and silence on the rest. That silence may reflect nothing more than the brevity of a subsequent-events note in an annual report. But until TVA says more, the honest description is that the downside protection is partly disclosed and partly assumed.

There is also the cohort question, which is TVA’s version of rationing — and its own candid warning. The fiscal 2027 cohort is 2,000 megawatts, first-come, first-served, and the first agreement — implying roughly 1,130 megawatts of chargeable capacity — takes more than half of it in a single signature. The cost of waiting is visible: a smaller remaining pool, and possibly a revised rate for later cohorts. That is rationing working as intended — and a concentration risk: one unnamed customer holds most of the first year’s room. TVA’s annual report lists unexpectedly low demand alongside unexpectedly high demand as risks that “could result in stranded costs, rate actions, curtailments, or a need for unplanned capital.” The charge prices one customer’s share of that risk; the system-level risk remains.

The gas behind the tariff

The most revealing pairing in the whole story is the one TVA made in the same board season: alongside the tariff, the board approved 1,550 megawatts of new gas generation targeted for 2032. TVA’s 2026 Integrated Resource Plan puts the Valley’s added generation need at 11 to 32 gigawatts by 2040, depending on how much of the prospective demand actually arrives. The charge prices the reservation. The gas is what will actually serve it.

That is the same generation gap behind every large-load tariff, and it is worth naming plainly. A tariff can allocate the cost of new capacity. It cannot create the capacity. Gas turbines can be ordered, permitted, and built on a schedule no other firm resource can match at that scale, which is why they sit at the center of TVA’s buildout, of Cheyenne’s 564-megawatt plant, and of nearly every data center power plan that has to deliver electrons before 2030. The alternatives on TVA’s books are further away: the Nuclear Regulatory Commission approved a construction permit in September for a GE Vernova Hitachi BWRX-300 small modular reactor at Clinch River, but TVA has not decided whether to build it. A permit is not a plant, and a 2032 gas target is not a 2027 energization.

Oregon is the instructive contrast here, the only one of the three that answers the fuel question inside the tariff itself. Pacific Power’s new resources serving large-load facilities must be non-emitting, and if fossil power serves one, the facility offsets the added emissions. TVA’s tariff carries no such requirement, and its filing says nothing about the emissions profile of the load it just signed. Neither does Black Hills’ announcement: the 564 megawatts of gas at Cheyenne Prairie is the firming layer for 2.1 gigawatts of undisclosed third-party resources. The three templates differ on who pays, on how the deal is structured, and on whether the fuel is the tariff’s business at all. Oregon says it is. TVA and Cheyenne, so far, do not.

What to watch

Five things will determine whether TVA’s tariff becomes the template or a footnote. The first is the cohort: how quickly the remaining roughly 870 megawatts of fiscal 2027’s 2,000 fills, and whether TVA revises pricing for the next round. The second is the customer: when TVA or the customer names the site, the counterparty-risk question gets an answer, and the energization timeline gets a date. The third is the installments: whether they arrive on schedule. The fourth is the build: whether the generation and transmission funded by the charge arrive on the timeline the reservation implies, and at anything near the estimated cost. The fifth is imitation: whether other federal power marketers and public power systems adopt a version of the charge — the mechanism travels less easily than the logic, since TVA’s board sets its own rates while most utilities answer to state commissions.

The bottom line

Two weeks after the first agreement under TVA’s Capacity Commitment Charge, the tariff has passed its first test and now faces the harder ones. It passed the test of whether a developer would sign under a $1.5 million-per-megawatt reservation price: one has, at a scale that takes more than half the first-year cohort. What it has not yet passed is the test of whether the charge covers the full incremental cost of serving that load, whether the load actually arrives, and whether the generation the charge is meant to fund gets built on time and on budget.

The comparison with Oregon and Cheyenne sharpens the point. Oregon bought durability through negotiation and a 10-to-30-year commitment, and answered the fuel question inside the tariff. Cheyenne bought precision through a contract, with collateral and full cost recovery, and let the utility build the plant itself. TVA bought speed and transparency: a published rate, a board vote, a signed agreement in six weeks. Speed is a real virtue in a market where interconnection queues stretch three to seven years. But speed is also what leaves the termination terms undisclosed, the energization date unstated, and the cost of serving the load untested. The $1.7 billion is a reservation, not a delivery.