FRACMOO

Power, markets, flexible RA,and the money behind the grid

Nov 2026
U.S. electricity demand, 2026 f'cast4,306 TWh
Reserve margin (PJM 2028/29)14.7%
Interconnection queue2,061 GW

Advertisement

GRID · Section

Electric Grid

Reliability, resource adequacy, and the transmission buildout β€” how the physical grid keeps up with demand.

Nov 28

GRID

DOE Declines Three Transmission Corridors

The Department of Energy formally closed the corridor process it began in December 2023, declining all three proposed designations β€” and in the same month offered $2.8 billion in conditional financing to a single merchant intertie.

By Mara Ellison ·

Nov 21

GRID

FERC's November Meeting: Build the Wires, but Prove Every Dollar in the Rate

At its November 19 open meeting, FERC authorized the affiliate sales behind NIPSCO's data-center buildout and sustained the incentives for a $1.7 billion transmission line β€” while sending New England transmission owners to hearing over the employee bonuses in their rates.

By Mara Ellison ·

Nov 20

GRID

The Sixth Filing: SPP Closes the Set on FERC's Large-Load Orders

Southwest Power Pool's response to FERC's large-load show-cause order is due today, completing the six-operator set β€” and unlike the other five, SPP is mostly defending a framework FERC has already accepted.

By Mara Ellison ·

Nov 17

GRID

The Bridge Is the Answer: What the Grid Operators Told FERC About Large Loads

Five grid operators owed FERC their large-load answers on November 16, and the filings in public view converge on the same bargain β€” connect early on available capacity, accept curtailment, and graduate to firm service β€” while SPP, due Friday, already has the template.

By Mara Ellison ·

Nov 13

GRID

The Grid Is Better Prepared for Winter. The Next Storm Will Be the Test.

NERC's cold-weather data shows 99 percent of winter capacity can operate at extreme cold temperatures, and the January Arctic storms proved the preparation works β€” but corrective action plans still hang open, and demand keeps rising into every margin the grid has bought.

By Mara Ellison ·

Nov 7

GRID

497 Actions, One Question: How States Plan for Large Loads

NCCETC counted 497 state actions on power decarbonization and resource planning in Q3 β€” and the dominant story is large load moving from the tariff docket into the integrated resource plan.

By Mara Ellison ·

Oct 27

GRID

The October Stress Test: Three Grids, Three Outcomes

PJM needed emergency authority, SPP reached its highest alert, and ERCOT rode through without a statewide appeal β€” the same hot, tight year exposed three different kinds of vulnerability.

By Mara Ellison ·

Oct 15

GRID

How SPP's CHILLS Service Answered the Problem That Killed PJM's IRAS

Months before FERC rejected PJM's curtailment framework, it accepted SPP's conditional transmission service β€” a voluntary, transmission-based bargain that lets large loads connect fast and be interrupted when the wires bind.

By Mara Ellison ·

Oct 7

GRID

Interconnection Queues Explained

Terawatts of generation are waiting years to connect to the grid. The queue is where energy ambitions meet transmission reality.

By Mara Ellison ·

Advertisement