On November 27, the Department of Energy filed a notice of availability that formally ends a process already over in substance. The notice publishes DOE’s July 2026 Report Concerning Designation of National Interest Electric Transmission Corridors, signed October 8 by Catherine Jereza, Assistant Secretary for Electricity, and concludes that there is not a sufficient basis to designate any of the three proposed corridors that advanced to the final phase of review in December 2024: the Tribal Energy Access Corridor across North Dakota, South Dakota, and Nebraska; the Southwestern Grid Connector across southeastern Colorado, New Mexico, and the Oklahoma Panhandle; and the Lake Erie–Canada Corridor across northern Pennsylvania and Lake Erie. The process begun in December 2023 is now complete, with no corridors designated.

The substance was announced more than three months ago: on August 12, Secretary of Energy Chris Wright said DOE would not move forward with designating any of the three corridors, after what he described as extensive review including public feedback and stakeholder input. The November notice is the formal close: the report of record, Federal Register publication expected November 30, ending a process that began covering ten proposed corridors spanning more than 3,500 miles.

What the notice actually says

DOE initiated the four-phase process in December 2023, after the 2023 National Transmission Needs Study, and selected three corridors in December 2024 to advance to Phase 3, the public-engagement phase, inviting comment under 89 FR 101597. The July report, DOE’s official determination, concludes that none of the three meets the statutory basis for designation under Section 216(a) of the Federal Power Act, 16 U.S.C. 824p. DOE’s public summary is spare: it reviewed the Needs Study, considered public and governmental input, and evaluated other information collected during the process. The report itself is the reasoning; DOE’s public summary offers no corridor-by-corridor findings analysis of the kind the statute’s criteria would invite.

That thinness matters: the public record establishes the outcome, the date, and the signature β€” not the corridor-by-corridor reasoning.

The backstop, with nowhere to go

The most consequential effect is the one this desk described nine days ago, when the Senate passed the Bipartisan American Affordability and Jobs Act: under current law, FERC’s backstop siting authority under Section 216(b) reaches only lines inside DOE-designated National Interest Electric Transmission Corridors. With no corridors designated, the authority has nowhere to be exercised. It has never been used to permit a line, and the November notice guarantees it will not be used under the current statute β€” because the geographic prerequisite does not exist anywhere in the country.

This is not the first time the corridor program has ended with nothing on the map. DOE designated two corridors in 2007, and the Ninth Circuit vacated both in 2011 in California Wilderness Coalition v. U.S. Department of Energy, holding that DOE had insufficiently consulted with affected states. The program sat dormant for more than a decade until the 2021 Infrastructure Investment and Jobs Act tried to repair it, adding a denial trigger to answer the Fourth Circuit’s 2009 Piedmont decision. The December 2023 process was the first attempt under the repaired statute, and it produced the same result as the original program: zero designated corridors, this time by administrative decline rather than judicial vacatur.

Section 2101 of BAAJA, passed 62–33 on November 19, eliminates the corridor prerequisite entirely and repeals DOE’s designation authority, replacing it with an informational congestion study every three years. If it becomes law, the November notice becomes a footnote: the backstop would no longer depend on corridors at all. The House is expected to take up the bill under suspension of the rules on or shortly after November 30 β€” the same day the DOE notice is expected to publish in the Federal Register.

What each corridor loses

The loss is different for each corridor. The Tribal Energy Access Corridor was drawn to connect tribal generation to the bulk transmission system, crossing tribal reservations β€” including Standing Rock, Cheyenne River, Rosebud, and Pine Ridge β€” where generation projects have struggled for market access. For tribal developers, designation was a signal that federal policy treated their interconnection as a national interest; without it, those projects negotiate access through the same processes that have left them waiting.

The Southwestern Grid Connector was the most contested of the three, supporting high-voltage direct-current transfer between the Eastern and Western Interconnections across southeastern Colorado, New Mexico, and the Oklahoma Panhandle β€” the seam where the country’s two synchronous grids barely touch. Landowner opposition in eastern Colorado was organized and vocal, and Representative Lauren Boebert celebrated the August announcement as a win for Colorado property owners. The decline leaves the East-West seam exactly where it was: a transfer constraint every reliability study identifies and no federal tool now addresses.

The Lake Erie–Canada Corridor was the most technically distinctive, a bidirectional cross-border path across northern Pennsylvania, Lake Erie, and into Ontario, raising questions β€” submerged freshwater cable engineering, treaty review, presidential permits β€” that no corridor designation has ever had to answer. Those questions stay unanswered.

The financing that was already gone

Designation was never only about siting; it was also the key to federal financing β€” and one of those keys was already taken off the ring before DOE acted. The first program is Transmission Facility Financing, created by Section 50151 of the Inflation Reduction Act: $2 billion in direct loan authority for facilities designated by the Secretary as necessary in the national interest under Section 216(a). A project in a designated corridor could have applied; a project outside one could not. But the unobligated funds under Section 50151 were rescinded by Section 50402 of the One Big Beautiful Bill Act of 2025. The loan program designation would have unlocked no longer has money to lend; the November notice closes a door Congress had already locked from the other side. The designation question is not moot β€” siting authority and other financing tools still turn on it β€” but the financing loss is smaller than the original $2 billion figure suggests.

The second is the Transmission Facilitation Program, the $2.5 billion revolving fund created by the Infrastructure Investment and Jobs Act. Its three tools are not equally corridor-dependent. Capacity contracts β€” DOE acting as an anchor tenant, buying up to 50 percent of a line’s capacity for up to 40 years β€” and TFP loans are available to eligible projects generally, including lines of at least 1,000 megawatts or upgrades of at least 500 megawatts in existing corridors. The public-private partnership tool, by contrast, is for transmission within a national interest electric transmission corridor, and it is now unavailable to any project in the three declined areas. Much of the commentary treats “federal financing” as a single switch. It is not. The decline narrows one tool and leaves two others open β€” the two DOE has actually used, including $1.3 billion in capacity-contract commitments announced in October 2023.

The other DOE move

Ten days before the corridor notice was filed, DOE made the other move that defines this month. On November 17, the department’s Office of Energy Dominance Financing announced a conditional loan commitment of up to $2.8 billion for Grid United’s Wyoming Intertie, a proposed 106-mile project in southeastern Wyoming that would add about 1.8 gigawatts of bidirectional transfer capacity between the Southwest Power Pool and the Western Electricity Coordinating Council regions, connecting the Aeolus substation near Medicine Bow to an HVDC back-to-back converter station near the Laramie River Station outside Wheatland. DOE estimates up to $39 billion in cost savings across 17 states β€” a federal projection whose methodology DOE did not detail.

The contrast is the story of the month: in the same month, DOE declined to designate any corridor β€” the geographic, programmatic tool for enabling many lines β€” and offered conditional financing to a single line. The Wyoming Intertie is a merchant project, developed by Houston-based Grid United, financed through the anchor-tenant model this desk described in its foundational piece on the transmission bottleneck, in which costs fall on contracted users rather than all regional ratepayers. The federal loan, structured as a loan guarantee involving the Federal Financing Bank and covering about 80 percent of construction costs over a 30-year term, would finance most of a project whose total cost is close to $4 billion.

But the commitment is conditional. Grid United must satisfy technical, legal, environmental, and financial requirements before DOE enters definitive financing documents and disburses funds. The company has secured options covering about 97 percent of the route, but it has not publicly identified capacity customers, and commercial capacity contracts, full right-of-way acquisition, and all permits are conditions of financial close. Permitting is expected in 2027 and 2028; construction could begin around 2030, with completion targeted for about 2033. A conditional commitment is not a funded loan, and no project financing should be described as money already lent.

The scale is worth one number. Existing transfer capacity between the Eastern and Western Interconnections totals just 1,320 megawatts, according to Grid United’s October 2026 open-house materials. The Intertie’s 1,800 megawatts would more than double that. That is both the promise and the indictment: a single merchant line can more than double transfer capacity at the seam because the seam is so narrow to begin with.

Read together, the two November decisions describe a coherent, if narrow, theory of what the federal government will do for transmission. It will not draw maps, designate regions where federal siting authority applies, or create the geographic predicate for programmatic financing. What it will do is finance individual projects, one at a time, through conditional commitments attached to a specific line, developer, and set of contracts. The corridor is a planning instrument; the loan commitment is a transaction. DOE has chosen the transaction.

There is a case for the transaction: a loan to a specific project with 97 percent of its route options secured and identified endpoints is a more surgical intervention than a wide geographic boundary that invites opposition from every landowner inside it, and it sidesteps the veto-point problem this desk has described as the central obstacle to building lines. There is also a case against it. A project-by-project approach builds lines where a developer can assemble land, customers, and financing β€” not the meshed, continent-scale network the reliability studies describe. The Wyoming Intertie more than doubles East-West transfer capacity β€” and still leaves the seam at about 3.1 gigawatts, a rounding error against the tens of gigawatts SPP’s own $23.7 billion plan is building inside a single region. Merchant lines are a valuable complement to regional planning, as this desk has written before. They are not a replacement for it.

What developers and commissions should actually do now

Nothing in the notice changes the permitting path for any specific project today: no corridor existed before it, and none exists after it. A developer whose project sat inside a proposed corridor loses a future option, not a current permit: no FERC backstop application can be filed for these areas under current law, no Transmission Facilitation Program public-private partnership can be structured around them, and the Section 50151 loan program, already rescinded, stays closed. Projects there proceed, if at all, through state siting, regional planning, or the merchant model β€” the paths that built nearly everything actually built in the last decade. For state commissions, the BAAJA debate in the House is now the only live vehicle for a federal backstop. For developers, the Wyoming Intertie is the template DOE is actually funding: a defined route, contracted capacity, and financing that does not depend on regional cost allocation. That template works for lines with identifiable customers, not for lines whose benefits are diffuse β€” reliability insurance, congestion relief spread across millions of bills β€” which is to say, most of the lines the studies say are needed most.

What to watch

Four things will tell us whether November was a pivot or a pause. First, the House: whether Speaker Johnson gets his two-thirds under suspension on or shortly after November 30, or whether BAAJA goes through the Rules Committee β€” and whether any amendment touches the transmission title. Second, the Wyoming Intertie’s conditions: whether Grid United identifies capacity customers and the conditional commitment converts to definitive financing documents. Third, the three declined areas: whether any project in those footprints advances without the federal tools designation would have provided. And fourth, whether DOE ever opens another corridor process, or whether the July 2026 report is the last word on a program that has now twice produced zero designations.

The question this desk posed in its foundational piece on the bottleneck has not changed: the grid is regional and continental, and the authority to build it is fragmented. The corridor program was one attempt to match the governance to the physics, and it has now failed twice β€” once in court, once by administrative decline. The merchant model, backed by a $2.8 billion conditional commitment, is the attempt that remains. Whether a country can build a continental grid one financed transaction at a time is the question November leaves open.