On Monday, November 16, five of the six regional grid operators owed the Federal Energy Regulatory Commission their answers in the large-load show-cause proceedings FERC opened on June 18. The Southwest Power Pool follows on Friday, November 20. Two filings are in public view as this edition goes to press: ISO New England filed its tariff proposal on November 13, and PJM filed its Fast Energization package on November 16. The other three operators carried proposals through board approval or stakeholder votes ahead of the deadline. Read together, the regions offer one coherent answer: a large load may connect on whatever transmission capacity is available, accept curtailment while its upgrades are built, and graduate to firm service when the work is done.
The proceedings are six separate cases under section 206 of the Federal Power Act, reported at 195 FERC paragraphs 61,211 through 61,216, each directed at one operator and its transmission owners: PJM (EL26-67), SPP (EL26-68), NYISO (EL26-69), MISO (EL26-70), CAISO (EL26-71), and ISO New England (EL26-72). In each, FERC preliminarily found that the operator’s tariff appears unjust, unreasonable, or unduly discriminatory because it lacks adequate provisions for large loads. The original 60-day clock would have put responses due August 17; every operator sought and received about 90 days of abeyance to run its proposal through stakeholders and file it as a tariff revision under section 205 instead. Nothing filed this week is a rule yet, and FERC has not acted on any of it.
New England files first, and prices flexibility
ISO New England’s filing is the most fully specified service menu in the proceedings, and the only one on the docket days before the deadline. Jointly filed November 13 by the ISO, the New England Power Pool, and the region’s transmission owners, it replaces a single service model with three — Firm, Interim, and Non-Firm Contract Demand Service. A large load is a commercial or industrial customer at a single site with gross peak demand of 50 megawatts or more, interconnecting above 60 kilovolts. The filing asks FERC to make the tariff effective November 14, 2026, and to shorten the comment period. Both are requests, not rulings. One detail for the record: the transmittal letter leaves its section 205 docket number blank, so the filing is identified for now by the show-cause docket that prompted it, EL26-72.
Firm service is the expensive end of the menu. A load taking firm service must designate new capacity resources of its own, and large loads are removed from the region’s Installed Capacity Requirement. Interim service is the bridge: temporary and non-firm, converting to firm once upgrades are finished or designated capacity comes online. Non-firm service is permanent, skips the bring-your-own-capacity requirement, and is studied around the load’s flexibility so fewer upgrades are needed. While on interim or non-firm service, a load can be re-dispatched when its local price exceeds a proposed $250 per megawatt-hour, a level ISO New England says local prices cross in about 1 percent of hours today.
Applications would carry a $50,000 fee, a $150,000 study deposit, and a readiness deposit of $10,000 per megawatt, with studies meant to finish in 90 days. The application and study process would open June 1, 2027, with the new transmission services following June 1, 2028.
PJM files the combined clock
PJM’s filing, made November 16, is the one the rest of the country was waiting for, because PJM is the largest grid operator and the one carrying the most large-load growth. Its centerpiece is Fast Energization, the design this desk covered on November 10: a single annual 12-month process — a four-month screening window, a seven-month system impact study, one month of agreement finalization — consolidating generation interconnection, merchant transmission interconnection, long-term firm transmission service, and large-load transmission service studies that today run on separate clocks. PJM says the combined study would cut projected study timelines from two years to one, asked FERC for a 60-day comment period, and asked for an order within 120 days.
Fast Energization sits on top of a service menu proposed in the same package: Network Integration Transmission Service in firm, interim, and fractional forms, and Contract Demand Service in firm and non-firm forms. The two families differ in what curtails them — capacity inadequacy on one side, a local transmission constraint on the other — and a load on interim or fractional service accepts curtailment on one of those bases for earlier access.
PJM made a second, separate filing the same day, and it may matter sooner. It proposes voltage and frequency ride-through requirements for large computational loads — facilities of 50 megawatts or more — with a requested effective date of January 16, 2027. PJM says it already serves about 10 gigawatts of such load and forecasts up to 30 gigawatts more by 2030. The trigger was the July 22 disturbance in Northern Virginia, when a normally cleared fault caused nearly 3.9 gigawatts of data center load to transfer to on-site generation. NERC’s computational-load standards package, approved on final ballot in mid-October, sets no industry-wide minimum ride-through requirement; PJM is now writing its own, as ERCOT did on August 1.
California, the Midwest, and New York
CAISO’s answer was fixed before the deadline arrived. On October 28, its Board of Governors approved the large-load framework it planned to file by November 16, built around a Flexible Interim Load Interconnection service — FILI — that lets a load of 50 megawatts or more connect before its network upgrades are complete. Participating transmission owners must have load study processes finishing within 60 to 90 days, with a monthly review window for large-load transmission additions outside the regular planning cycle.
California’s framework has one consequential omission, and the answer period will press on it. The approved package contains only the interim service. A permanent flexible option — the FLIP service floated in an August straw proposal — was dropped, with a permanent flexible option and arrangements for electrically proximate generation deferred to 2027. Constellation Energy, in a comment letter dated October 28, supported approval while urging the board to direct CAISO to include a permanent flexible transmission service option in the FERC filing. The test for FERC will be whether FILI is bounded tightly enough that it does not become the permanent rule by default.
MISO’s answer is the furthest along in public and the most incomplete in one respect. In an August 28 filing it proposed interconnection reliability requirements for large loads — visibility, ramp-rate, and disturbance ride-through rules — defining a large load as 50 megawatts or more at a single substation, with a computational-load carve-out at 25 megawatts of IT-equipment demand, seeking a December 4 effective date. Then, on October 2, it proposed the 120-day Large Load Addition Resource Study, or LARS, studying a load above 200 megawatts together with new generation in the same local resource zone, in parallel, with both tied together for 15 years. What MISO has said is still to come is the cost question: cost-shifting protections, the pro forma cost recovery agreement, financial security, and transparency provisions FERC demanded.
NYISO starts from a different problem statement. Its tariff already had load interconnection procedures and a distinctive financial-reservation model, but FERC preliminarily found the study process insufficiently sophisticated, the application process in need of enhancement, and the netting of co-located generation against co-located load potentially unjust and unreasonable. Its Management Committee considered the proposed reforms on November 2: a Large Load Integration Procedures track with readiness deposits and queue-withdrawal rules; withdrawal services — firm, non-firm, and zero withdrawal — separating the right to take power from the right to sell capacity; and a co-located load aggregation model treating load and generation separately rather than netting them, with a 15-year term proposed for resources partnering with loads seeking firm withdrawal service.
SPP: the template, due Friday
SPP enters the week further ahead than any other operator, and its deadline is four days later — November 20 — because its joint abeyance motion with its transmission owners asked for 95 days. It already had a High Impact Large Load process (HILL) and a companion generation assessment (HILLGA), accepted effective January 15, 2026, pairing a large load with shovel-ready generation and studying them together. In June, FERC accepted a further piece, Conditional High Impact Large Load Service (CHILLS), effective July 1, 2026, letting a very large load take non-firm, interruptible service for up to seven years while firm generation and upgrades are lined up. CHILLS is the most generous early-access product in any region, and the most exposed: SPP can curtail a CHILLS customer when the system is constrained or in emergency conditions, with no tariff cap on how often or how long curtailment can last.
SPP’s filing therefore has a different job: less invention, more completion. The questions are whether HILL, HILLGA, and CHILLS satisfy the order’s remaining items — above all the pro forma cost recovery agreement and transparency provisions, and a mechanism to credit large-load cost-recovery payments toward transmission owners’ revenue requirements — with SPP’s pending clarification filing asking FERC to rule by December 1. CHILLS is the template the other regions are converging on: a bridge with a price, a trigger, and a deadline.
Who pays, and who waits
The filings converge on the bridge. They diverge on the two questions that will decide whether the bridge works: who pays for the upgrades, and how long a load may sit on interim service before it must convert or leave. On payment, the mechanism FERC keeps returning to is the cost recovery agreement — a standard, pro forma agreement among the operator, the transmission owner, and the transmission customer taking service on behalf of the large load, backed by financial security, obliging the load to cover the costs incurred to serve it, including network upgrades, even if the project is canceled or operates below its anticipated demand.
On waiting, the durations differ in ways that will shape developer behavior. SPP’s seven-year clock is the longest bridge on offer and the most explicit about its end: after the agreement terminates, the customer cannot take capacity at that delivery point beyond the level of any transmission service it was otherwise granted. ISO New England’s interim service converts to firm when upgrades finish or designated capacity comes online, and lasts up to seven years or until the upgrades are in service, whichever is longer — the conversion, not the calendar, is the backstop.
The filings compress the study phase, not the construction phase. A 90-day study in New England, a 120-day joint study in MISO, a 12-month combined clock in PJM — all give an answer sooner. None pours concrete faster. The scale behind the question is large: Latitude Media has reported that utilities have signed about 120 gigawatts of data center contracts — roughly 22 percent of the 537 gigawatts they report — against about 22 gigawatts running today.
The line, the pushback, and what to watch
The bridge model survives because of a legal distinction the regions have learned to respect since October, when FERC approved PJM’s large-load registry but rejected its Interim Resource Adequacy Service on jurisdictional grounds. IRAS would have put curtailment obligations directly on new large loads — mostly retail customers — and effectively picked which retail customers would be curtailed first in a supply emergency, choices that belong to the states. CHILLS, accepted four months earlier, never approaches that line: it is a transmission service, offered under the transmission tariff, with interruption keyed to thermal and voltage limits on the wires, and it is elective — a load chooses conditional service in exchange for faster access.
The pushback is already on the record, and it goes to the design’s central choice in PJM. In an October 28 letter to PJM’s president and chief executive and the chair of its Board of Managers, the American Clean Power Association argued that studying all generator interconnection requests and large-load transmission service requests in a single annual cluster could materially slow generator interconnection precisely when new generation is most needed. Large load brings a materially different risk profile, the letter says, and PJM has not shown how generation timelines will be preserved. Its ask is narrow: limit the November 16 filing to a targeted response to the show-cause order. PJM filed the whole package anyway.
One thread running alongside the proceedings is the permitting bill: on November 9, the Senate voted 73–25 for cloture on the motion to proceed, and the House still stands between the bill and the grid. If it becomes law, it addresses the construction side — the years of permitting and siting that no study clock can compress — while the filings address the connection side.
The deeper watch item is operational, and it is the same in every region: the first conversion. An interim service exists on paper until a load actually connects under it, is curtailed under it, and converts to firm service when its upgrades finish. The filings’ answer, in every region, is the same bargain — speed in exchange for firmness, with the bill assigned to the load that caused it. The bargain is now on the docket. Whether it is just and reasonable is FERC’s to decide.