The filings are in, and they can now be read as filings rather than previews. On Monday, November 16, five of the six regional grid operators submitted their answers to the Federal Energy Regulatory Commission’s June 18 large-load show-cause orders. ISO New England had already filed on Friday, November 13; the Southwest Power Pool follows on Friday, November 20. What arrived is not a single federal rule but five separate tariff proposals, each filed under section 205 of the Federal Power Act in a new docket, each claiming to answer the preliminary finding in its own section 206 proceeding. None of them is approved. FERC has not acted on any of them, and the answer period runs to December 16.

That distinction matters more this week than it did last week, because the filings are now specific enough to be mistaken for settled policy. They are not. Each is an operator’s proposal, shaped by months of stakeholder negotiation, and each now faces the same test: whether FERC finds it satisfies the show-cause order, accepts it subject to conditions, sets it for hearing, or prescribes a remedy of its own.

New England: the filing with a docket number

ISO New England’s proposal is the most fully specified of the five, and the only one filed days before the deadline. Jointly filed November 13 by the ISO, the New England Power Pool, and the Participating Transmission Owners Administrative Committee, it is listed under docket ER27-484-000. The filing replaces a single service model with three: Firm, Interim, and Non-Firm Contract Demand Service. A large load is a commercial or industrial customer at a single site with gross peak demand of 50 megawatts or more, interconnecting above 60 kilovolts. The filing asks FERC to make the tariff effective November 14, 2026, and to shorten the comment period. Both are requests, not rulings.

The three services are the menu the other regions are converging on, stated here in the clearest form. Firm service is the expensive end: a load taking firm service must designate new capacity resources of its own, and large loads are removed from the region’s Installed Capacity Requirement. Interim service is the bridge — temporary and non-firm, converting to firm once upgrades are finished or designated capacity comes online, lasting up to seven years or until the upgrades are in service, whichever is longer. Non-firm service is permanent, skips the bring-your-own-capacity requirement, and is studied around the load’s flexibility so fewer upgrades are needed. While on interim or non-firm service, a load can be re-dispatched when its local price exceeds a proposed $250 per megawatt-hour, a level ISO New England says local prices cross in about 1 percent of hours today.

The filing also answers FERC’s transparency demand directly: ISO New England proposes to maintain a public list on its website of the network upgrades identified for each large load, categorized by upgrade type, with cost estimates attached. Applications would carry a $50,000 fee, a $150,000 study deposit, and a readiness deposit of $10,000 per megawatt, with studies meant to finish in 90 days. The application and study process would open June 1, 2027, with the new transmission services following June 1, 2028.

PJM: the combined clock, and the owners’ separate filing

PJM’s filing is the one the rest of the country was waiting for, because PJM is the largest grid operator. Its centerpiece is Fast Energization: a single annual 12-month process — a four-month screening window, a seven-month system impact study, one month of agreement finalization — consolidating generation interconnection, merchant transmission interconnection, long-term firm transmission service, and large-load transmission service studies that today run on separate clocks. PJM says the combined study would cut projected study timelines from two years to one, asked FERC for a 60-day comment period, and asked for an order within 120 days. The package also proposes a service menu: Network Integration Transmission Service in firm, interim, and fractional forms, and Contract Demand Service in firm and non-firm forms, with interim and fractional service accepting curtailment for earlier access.

In its filing, PJM said the proposal is designed to address “insufficiently fast interconnection processes for load and generation, parallel and duplicative study processes, speculative requests, limited visibility into the drivers of transmission upgrades, and an ongoing resource adequacy shortfall.” The proposal also addresses co-location and behind-the-meter generation rules that were at issue in a separate show-cause proceeding.

The PJM transmission owners filed separately the same day, and their filing may matter as much as the operator’s. It proposes the owners’ own tariffs establishing rates, cost allocation, cost recovery mechanisms, financial protections, revenue-crediting requirements, and transparency measures for transmission service they provide to co-located loads and large loads. That split is structural: PJM operates the system, but the transmission owners build the wires and recover their costs, and the cost question lives in the owners’ filing as much as in PJM’s. It is also the filing that gives states what PJM says they need: transparent access to the transmission costs driven by large loads, so states can bill those loads for them.

PJM made a second, separate filing the same day, and it may matter sooner than either. It proposes voltage and frequency ride-through requirements for large computational loads — facilities of 50 megawatts or more — with a requested effective date of January 16, 2027. PJM says it already serves about 10 gigawatts of such load and forecasts up to 30 gigawatts more by 2030. The trigger was the July 22 disturbance in Northern Virginia, when a normally cleared fault caused nearly 3.9 gigawatts of data center load to transfer to on-site generation.

California: the interim bridge, filed

CAISO’s filing was the most predictable of the five, because its answer had been fixed before the deadline arrived. On October 28, its Board of Governors approved the large-load framework it planned to file by November 16, built around a Flexible Interim Load Interconnection service — FILI — that lets a load of 50 megawatts or more connect before its network upgrades are complete. The filing, made November 16, carries that framework to FERC.

The package creates streamlined paths for large loads to connect, with standardized application information, deposits, milestones, study coordination, and service agreements, and offers new service options for flexible large loads that can cut their electric use when transmission capability is unavailable. Participating transmission owners must have load study processes finishing within 60 to 90 days.

California’s framework still carries the consequential omission this desk flagged before the deadline. The filed package contains only the interim service. A permanent flexible option — the FLIP service floated in an August straw proposal — was dropped, with a permanent flexible option and arrangements for electrically proximate generation deferred to 2027. Constellation Energy, in a comment letter dated October 28, supported approval while urging the board to direct CAISO to include a permanent flexible transmission service option in the FERC filing.

MISO: the cost question, answered on paper

MISO’s filing is the one that changed the most between preview and submission, and the change is the one that matters. In an August 28 filing it proposed interconnection reliability requirements for large loads — visibility, ramp-rate, and disturbance ride-through rules — defining a large load as 50 megawatts or more at a single substation, with a computational-load carve-out at 25 megawatts of IT-equipment demand. Then, on October 2, it proposed the 120-day Large Load Addition Resource Study, or LARS, studying a load above 200 megawatts together with new generation in the same local resource zone, in parallel, with both tied together for 15 years. What MISO had said was still to come was the cost question: cost-shifting protections, the pro forma cost recovery agreement, financial security, and transparency provisions FERC demanded.

The November 16 filing supplies that missing piece, at least on paper. MISO says its proposal builds on the earlier filings and includes a Large Load Project Review process, new transmission service options, and tariff revisions and pro forma cost recovery agreements designed to prevent cost shifting onto existing customers. In a separate filing the same day, MISO proposed a Grid Responsive Integration Transmission Service for large loads that can limit their electric use under certain price and reliability conditions. That is the filing’s vulnerability: the cost recovery agreement is only as strong as its enforcement, and the answer period will test whether the agreement as filed actually binds a load that shrinks, delays, or disappears after the wires are built.

New York: withdrawal service, and a state compromise

NYISO’s filing starts from a different problem statement than the other four, and its proposal reads accordingly. Its tariff already had load interconnection procedures and a distinctive financial-reservation model, but FERC preliminarily found the study process insufficiently sophisticated, the application process in need of enhancement, and the netting of co-located generation against co-located load potentially unjust and unreasonable. Its Management Committee considered the proposed reforms on November 2; the filing made November 16 carries them to FERC. The New York transmission owners filed a complementary large-load proposal the same day.

The centerpiece is a pair of new transmission services — Firm Withdrawal Service and Non-Firm Withdrawal Service — that reflect the distinctive characteristics of NYISO’s transmission model and of co-located large loads, large loads with behind-the-meter generation, and flexible large loads. The proposal separates the right to take power from the right to sell capacity, with non-firm loads required to curtail when directed and without compensation. On co-location, it treats load and generation separately rather than netting them, with a 15-year term proposed for resources partnering with loads seeking firm withdrawal service.

The filing also includes a compromise approach to resource adequacy requirements, called the State Exempt Load Project exception, which aims to reconcile NYISO’s reliability responsibilities with the New York Public Service Commission’s resource adequacy authority. Whether FERC accepts that division of labor is one of the answer period’s open questions.

What FERC does next

The procedural frame is the same for all five filings, and it is worth stating plainly because the filings will now be discussed as though they were rules. They are responses in pending proceedings, not approved tariffs. Under the abeyance orders FERC issued in August, a respondent that makes a section 205 filing addressing the Commission’s preliminary findings by November 16 has its obligation to answer the show-cause order suspended, and the proceeding stays in abeyance pending further Commission direction. Answers to the responses in the section 206 dockets are due December 16.

What happens after that is FERC’s choice, filing by filing. It can accept a filing, accept it subject to condition, set it for hearing, or prescribe a remedy itself. The PJM experience this autumn — a registry accepted, a curtailment plan rejected on jurisdictional grounds, a backstop procurement suspended for five months — is a reminder that FERC does not move on the applicant’s schedule.

The line, the pushback, and what to watch

The filings converge on the bridge, and they diverge on the two questions that will decide whether the bridge works: who pays for the upgrades, and how long a load may sit on interim service before it must convert or leave. On payment, the mechanism FERC keeps returning to is the cost recovery agreement — a standard, pro forma agreement among the operator, the transmission owner, and the transmission customer taking service on behalf of the large load, backed by financial security, obliging the load to cover the costs incurred to serve it, including network upgrades, even if the project is canceled or operates below its anticipated demand. MISO’s filing now includes one; the PJM transmission owners’ filing proposes one; ISO New England’s filing pairs one with a public upgrade list. The question in each case is the same: does the agreement as written actually bind?

On waiting, the durations differ in ways that will shape developer behavior. SPP’s seven-year clock — its Conditional High Impact Large Load Service, accepted effective July 1, 2026 — is the longest bridge on offer and the most explicit about its end. ISO New England’s interim service converts to firm when upgrades finish or designated capacity comes online, and lasts up to seven years or until the upgrades are in service, whichever is longer. CAISO’s interim service has no permanent flexible successor yet, which makes its duration the question the answer period will press hardest.

The filings compress the study phase, not the construction phase. A 90-day study in New England, a 120-day joint study in MISO, a 12-month combined clock in PJM, a 60-to-90-day study window in California — all give an answer sooner. None pours concrete faster. The deeper watch item is operational, and it is the same in every region: the first conversion. An interim service exists on paper until a load actually connects under it, is curtailed under it, and converts to firm service when its upgrades finish. The bargain is now on the docket, in five separate filings, with answers due December 16 and SPP’s filing still to come on Friday. Whether it is just and reasonable is FERC’s to decide.