On Thursday, November 19, the Federal Energy Regulatory Commission held its monthly open meeting, and the electric agenda read like the other half of the story this desk has been covering all week. On Monday, five grid operators filed their large-load tariff proposals, answering FERC’s June show-cause orders with a bridge model: connect early, accept curtailment, graduate to firm service. The Southwest Power Pool filed its answer on Friday, November 20, closing the set. The meeting dealt with the question the filings mostly defer: who pays, and what exactly goes into the rate. The Commission cleared the way for new wires and new supply to serve data centers in Indiana and Pennsylvania, and it sent New England’s transmission owners to hearing over the cost of their own employees’ bonuses. FERC is not slowing the buildout. It is tightening its grip on the bill.

New England: the bonus fight goes to hearing

The first two electric items, E-1 and E-2, address formal challenges to the New England transmission owners’ 2025 annual updates to their transmission formula rates, in Docket No. ER20-2054-000. Both orders set hearing and settlement judge procedures to review whether the employee incentive compensation costs in the updates are just and reasonable. E-1 addresses the challenge to Central Maine Power’s update; E-2 covers Connecticut Light and Power Company, NSTAR Electric Company (East), NSTAR Electric Company (West), and Public Service Company of New Hampshire.

The challenge comes from the New England States Committee on Electricity, known as NESCOE, which filed its formal challenge on February 9, 2026. NESCOE asked FERC to direct Central Maine Power to remove financial-based employee incentive compensation costs from its Regional and Local Network Service rates, with refunds, or to open a section 206 proceeding. The states’ argument is that incentive payouts tied to financial targets do not benefit customers and should not be recovered in formula rates. The November 19 orders do not resolve the merits; they set the process, and the transmission owners will now have to defend the costs at hearing.

One number in the record shows what is at stake. On December 5, 2025, the Participating Transmission Owners Administrative Committee, on behalf of Central Maine Power, submitted a supplemental informational filing to the July 31, 2025 annual informational filing, reducing CMP’s 2026 Local Network Service annual transmission revenue requirement from $151,420,099 to $136,774,147. A cut of about $14.6 million, roughly 10 percent, for a single service in a single year β€” a measure of how much money rides on the inputs to a formula rate.

Why incentive pay is a rate case

Employee incentive compensation sounds like a human-resources matter. In a formula rate it is a cost-of-service question, and the distinction FERC will have to draw is a familiar one. Utilities have long recovered the cost of compensating their employees in rates, including performance-based pay tied to operational goals β€” safety, reliability, customer service β€” on the theory that pay structured to reward good performance benefits customers. What the states challenge is the financial-based slice: bonuses tied to earnings or stock price. The argument is that a payout triggered by the parent company’s financial results rewards shareholders’ outcomes, not customers’ service, and recovering it in transmission rates makes customers pay for the company’s own upside.

The transmission owners’ position, as it will presumably be made at hearing, is that incentive compensation is part of the market cost of attracting and retaining the workforce that runs the system. FERC has accepted that argument in some cases and rejected it in others, and the outcomes have often turned on the specifics: how much of the pay is financial-based and whether the utility can show a customer benefit. A hearing, rather than a summary order, is the Commission’s way of saying the record does not yet answer those questions. The rates at issue continue to be collected in the meantime, subject to refund.

Indiana: the affiliate sales that make GenCo work

If E-1 and E-2 are the meeting’s scrutiny half, E-4 is its facilitation half. In Docket Nos. ER26-3474-000 and ER26-3475-000, FERC granted authorization for Northern Indiana Public Service Company, known as NIPSCO, to purchase energy and capacity at market-based rates from an affiliate, NiSource Generation Company LLC β€” GenCo β€” so that NIPSCO can serve the increased load in its service territory. Filed August 3, 2026, under section 205 of the Federal Power Act, the applications cover two power purchase agreements, dated November 7, 2025, and April 16, 2026.

The two agreements serve two different data center developers under state-approved special contracts. The first, in Docket No. ER26-3474-000, supports retail service to Amazon Data Services, Inc., ramping up to 2,400 megawatts by 2032. The second, in Docket No. ER26-3475-000, supports service to Midnight Sun Ventures LLC, ramping up to 300 megawatts by 2030. GenCo plans to build up to 3,000 megawatts of generation in the Midcontinent Independent System Operator market to serve them: two 1,300-megawatt combined cycle gas turbines and a 400-megawatt battery.

The FERC authorization is the federal piece of a structure NiSource has been building all year. The regulated utility, NIPSCO, keeps serving its existing customers. The unregulated affiliate, GenCo, builds the generation for the new large loads and sells it to NIPSCO at market-based rates. As NiSource describes it, the design insulates NIPSCO’s captive customers from the incremental costs of serving the data centers: the large-load customers fully fund the generation and transmission needed to serve them. The company projects about $1.75 billion in savings for existing NIPSCO electric customers over the life of the data center contracts β€” as much as $140 per customer annually. Those are company projections, not savings already delivered, and they depend on the loads materializing on schedule.

The same GenCo structure sits behind the Microsoft agreement NiSource announced October 16, 2026: a 20-year deal for Microsoft’s planned northwest Indiana data center campus, under which Microsoft is expected to begin taking service in 2028, the GenCo pool grows by about 1,100 megawatts, and 600 megawatts of battery storage is contracted under a long-term tolling agreement. The E-4 dockets are the Amazon and Midnight Sun agreements, not the Microsoft deal, but the authorization covers the same affiliate-sales mechanism. The Indiana Utility Regulatory Commission has already approved the framework for NIPSCO’s purchases from GenCo despite opposition from the state’s Office of Utility Consumer Counselor.

That approval is not a blank check. A market-based rate sale between affiliates is legal only if the Commission is satisfied the affiliate cannot exercise market power and the transaction does not shift costs to captive customers β€” the classic risk being an unregulated affiliate selling to its regulated sister at an inflated price that retail customers then absorb. Market-based rate authority is revocable, and the agreements remain subject to FERC oversight. The state approval, the federal authorization, and the special contracts form a three-legged stool: a load that does not ramp, a plant that does not get built, or a cost landing on the wrong customers puts the others under strain.

Pennsylvania: the incentives survive, the ROE waits

E-5, in Docket No. ER26-1734-002, is the meeting’s most consequential item for transmission developers, and it requires a careful reading, because the headline and the detail point in different directions. The order sustains the Commission’s July 10, 2026, order, 196 FERC ΒΆ 61,015, which granted Kammer Juniata Transmission certain transmission incentive rate treatment for the Kammer Juniata Project. What it sustained, precisely, is an order that granted the incentive package while sending the formula rate β€” including the return on equity β€” to hearing.

Kammer Juniata Transmission filed on March 12, 2026, as amended May 12, seeking formula rates and incentives for the 222-mile, 765-kilovolt line. The July 10 order granted three incentives effective July 11, 2026: recovery of 100 percent of prudently incurred costs if the project is abandoned for reasons outside Kammer’s control; inclusion of 100 percent of construction work in progress in rate base; and a hypothetical capital structure of 60 percent equity and 40 percent debt until the project is placed in service. It conditionally granted a 50-basis-point return-on-equity adder for regional transmission organization participation, subject to the total return staying within the zone of reasonableness set in the hearing.

What the July 10 order did not do is grant the 10.75 percent base return on equity Kammer requested. The Commission found the formula rate template had not been shown to be just and reasonable and instituted a section 206 proceeding to examine it, including the proposed return on equity and proxy cost of debt. The November 19 order sustains that disposition. The incentives stand. The return is still to be litigated.

The project is large by any measure: approximately 222 miles of new 765-kilovolt transmission, in segments of about 114 miles and 108 miles connecting to new 765/500-kilovolt substations at Buttermilk Falls and Mountain Stone, traversing ten counties in Pennsylvania and one in West Virginia. The estimated cost is approximately $1.7 billion, with an anticipated in-service date of June 2031. It was selected in February 2026 as Proposal 237 in PJM’s 2025 Regional Transmission Expansion Plan Window 1 and is being developed by NextEra Energy and Exelon; the filing states the facilities are driven by data center load. The Pennsylvania Office of Consumer Advocate, protesting April 7, 2026, argued the requested base return was excessive and estimated the project could raise Pennsylvania customer rates by up to $678 million. Kammer has not yet applied for certificates of public convenience and necessity from the Pennsylvania and West Virginia commissions, and has said an application to the Pennsylvania commission is unlikely before 2027.

The pattern, and the PacifiCorp thread

The November 19 orders continue a pattern this desk has been tracking since the start of the month. On November 2, FERC rejected PacifiCorp’s request to let its transitional-cluster projects withdraw for nine times study cost even after signing an interconnection agreement, holding that the standard penalty β€” 20 percent of identified network upgrade costs β€” applies once the agreement is executed. The order was unprotested; Commissioner Lindsay S. See dissented, arguing the tariff did not compel the result.

The November 19 meeting is the same instinct applied to money rather than to queue discipline. In PacifiCorp, FERC refused to let a transition soften the rule that makes the new interconnection process work. In New England, it refused to decide on the papers whether financial-based bonuses belong in transmission rates. In Pennsylvania, it kept the incentives that make a $1.7 billion line financeable while holding the return on equity for a hearing. In Indiana, it authorized the affiliate sales letting a utility serve 2,700 megawatts of new data center load while keeping the cost off existing customers. The through line is not hostility to building. It is a refusal to let the building happen on unexamined rates.

That posture has a cost of its own. Hearings take time. The New England incentive-compensation question will now work through settlement judge procedures and, if necessary, an administrative law judge β€” months, at least, with the challenged costs in rates subject to refund. Kammer Juniata is in the same posture: the incentives are granted and the project can proceed toward its 2031 in-service date, but the return that determines what the line earns is unresolved. Developers must now price two uncertainties at once: whether the line gets built, and what it will be allowed to earn.

What to watch

Three things will determine whether the November 19 meeting is remembered as routine or as the moment the cost question caught up with the buildout. The first is the New England hearing. Watch whether the parties settle before litigating, and if they do, whether the settlement draws a line between operational and financial incentive pay that other regions can use. Removing financial-based bonuses from the formula rate outright would be the most consequential outcome.

The 10.75 percent base return was the most contested number in the July filing, and the hearing will test it against the zone of reasonableness with evidence rather than argument. The state certificates are the other gate: the project cannot be built without them, and the Pennsylvania commission’s concerns about cost allocation have not gone away.

The third is the Indiana buildout itself. The E-4 authorization is the federal green light for a structure that now carries Amazon’s 2,400 megawatts, Midnight Sun’s 300 megawatts, and Microsoft’s 1,100 megawatts, with up to 3,000 megawatts of new generation to be built. The loads ramp through 2030 and 2032; the generation has to be there when they do. The first test of the GenCo structure will not be a FERC order. It will be whether the plants get built on schedule and the savings NiSource projects for existing customers actually appear on bills. The orders will be posted to FERC’s eLibrary; the published summaries are, by the Commission’s own statement, only a general synopsis.

The large-load filings answer how a data center connects. The November 19 meeting answered, in part, how it gets paid for. The two answers are now on the same docket, and the next year of proceedings will be spent reconciling them.