The filings are done. Between November 13 and November 20, all six grid operators under the Federal Energy Regulatory Commission’s jurisdiction answered the June 18 show-cause orders on large-load interconnection. This desk covered what the filings propose on November 17 and 18. What those pieces did not answer, and what every developer with a site under contract is now asking, is simpler: when does any of this actually take effect?

The answer is a calendar, not a date. Most of the new tariffs would take effect in early 2027, if FERC accepts them. The services that make “speed to power” real do not start until 2028 or 2029 in the regions where they matter most. A developer planning a 2027 energization is planning under the old rules. A developer planning for 2029 is planning under rules that do not yet exist.

What “effective” actually means

Start with the dates that look like progress. NYISO requested a February 1, 2027 effective date for its Large Load Integration Procedures. CAISO requested February 16, 2027 for most of its reforms. MISO requested February 14, 2027. PJM requested March 16, 2027 for its new services and netting limit. SPP requested February 2027 for the first two of its three proposals. Read together, that is a coherent sentence: the tariffs take effect in early 2027.

But a tariff taking effect is not the same as a service being available. In several regions, the February and March dates switch on the study process, the fees, the cost recovery agreements, and the transparency provisions — the machinery around the service. The service itself starts later.

ISO New England is the clearest case. Its filing asks FERC to make the tariff effective November 14, 2026 — the earliest date of any of the six — and to shorten the comment period. But the application and study process would not open until June 1, 2027, and the new transmission services themselves — Firm, Interim, and Non-Firm Contract Demand Service — would not begin until June 1, 2028. A filing that asks for an effective date in 2026 delivers its first service eighteen months later. Both dates are real. Only one of them puts power on a site.

PJM: the twelve-month clock that starts late

PJM’s filing is the one the rest of the country was watching, because PJM is the largest grid operator and the one carrying the most large-load growth. Its centerpiece is Fast Energization: a single annual twelve-month process — a four-month screening window, a seven-month system impact study, one month of agreement finalization — consolidating four study tracks that today run on separate clocks. PJM says the combined study would cut projected study timelines from two years to one, and asked FERC for a 60-day comment period and an order within 120 days.

Here is the calendar behind that promise. The Fast Energization process would begin only after the current cycle’s second decision point, expected in late November 2027. A twelve-month cycle starting then does not finish until 2029. A developer entering the new process is looking at a study answer in 2029, with energization and network upgrades after that.

What does start sooner in PJM is the service menu. The March 16, 2027 requested effective date would make Interim Network Integration Transmission Service and Firm and Non-Firm Contract Demand Service available to any large load, not only co-located ones. The transmission owners’ companion filing sets cost recovery terms, with minimum revenue commitments of 80 to 100 percent of the firm service benchmark. And the separate ride-through filing — requirements for large computational loads of 50 megawatts or more — carries a requested effective date of January 16, 2027, the fastest-moving piece of the PJM package, driven by the July 22 disturbance in Northern Virginia, when a normally cleared fault caused nearly 3.9 gigawatts of data center load to transfer to on-site generation. The scale explains both the urgency and the wait: PJM’s 2025 load forecast projected 32 gigawatts of peak demand growth between 2024 and 2030, of which 30 gigawatts was attributable to data centers.

MISO: flexible service, 2029

MISO’s flexible service is the furthest out of any of the six. Its Grid Responsive Integration Transmission Service — GRITS — would let a large load take part of its demand as firm service and part as non-firm, curtailing when the locational price exceeds $100 per megawatt-hour and during capacity advisories. MISO estimates the service would still be available in more than 95 percent of hours. But MISO says it cannot offer GRITS until January 2029. The February 14, 2027 effective date it requested covers the rest of the package: the Large Load Project Review process, running three study cycles a year at about five months each, a Firm Service Step Up that lets loads move to firm service in increments as transmission capability becomes available, and the pro forma cost recovery agreements FERC demanded.

MISO’s earlier filings fill in the path to 2029. The Large Load Addition Resource Study, filed October 2, studies a load above 200 megawatts together with new generation in the same local resource zone, paired for 15 years, on a 120-day clock. What a developer cannot do before 2029 is buy the flexible service itself — and that 2029 commencement is one of the items analysts expect FERC to press MISO to justify, alongside the 200-megawatt threshold.

New England: June 2028, with a capacity condition attached

ISO New England’s calendar is the most precisely dated of the six, and the most demanding. Applications open June 1, 2027. Studies run 90 days from execution of the study agreement, with extensions where coordination with a cluster study is needed. The new services begin June 1, 2028. Interim and non-firm customers are re-dispatched whenever their local price exceeds $250 per megawatt-hour, a level ISO New England says local prices crossed in about 1 percent of hours between 2021 and 2025.

The date that matters most in New England is not on the service calendar. It is the capacity condition attached to firm service. Under the proposed Bring Your Own New Capacity requirement, a large load seeking firm transmission service must secure incremental new capacity, and large loads are removed from the region’s Installed Capacity Requirement. That requirement is also the filing’s biggest legal risk: it resembles the bring-your-own-capacity terms FERC rejected in PJM’s Interim Resource Adequacy Service proposal in October, which FERC found appeared to intrude on state retail authority. ISO New England’s version is structured differently — non-firm service is something a load chooses, not a penalty imposed on it — but the resemblance is close enough that no developer should treat the June 2028 firm-service date as certain.

New York: the longest study, the earliest tariff

NYISO holds both ends of the calendar at once. Its Large Load Integration Procedures carry the earliest requested effective date — February 1, 2027 — and the longest study cycle: a 90-day system impact study, followed by a year-long assessment of load integration, for roughly 18 months to two years in total. NYISO acknowledges this exceeds the 60-to-90-day timeline FERC contemplated. The related market rule changes would take effect June 1, 2028.

The New York proposal is also the one with the most visible state compromise built into it. Projects identified by the Department of Public Service can qualify for firm service without NYISO’s standard resource adequacy test, under the State Exempt Load Project exception, aimed at reconciling NYISO’s reliability role with the Commission’s resource adequacy authority. Whether FERC accepts that division of labor is one of the answer period’s open questions. Non-firm loads are curtailed when their local price reaches $200 per megawatt-hour.

SPP and CAISO: the two services that already exist

SPP is the furthest along, because it is building on services that already exist. Its High Impact Large Load services were approved by FERC on January 14, 2026, and its Conditional High Impact Large Load Service — the bridge that lets a large load take non-firm service for up to seven years while firm service and upgrades catch up — was approved June 5, 2026. The November 20 filing adds three things: an evaluation of alternative transmission technologies in the large-load studies, a Load Safe Harbor Limit making customers pay for delivery-point upgrade costs above the lesser of $25 million or $500,000 per megawatt of service requested, and Price Adaptive Load Service — PALS — a non-firm service with one-to-ten-year terms, available to any load, whose withdrawals are governed by bids capped at $25 per megawatt-hour and dispatched to zero above it.

SPP requested February 2027 effective dates for the first two proposals. PALS has no effective date yet; SPP said it will set one later, and the service is targeted for the second quarter of 2028 — the only operator whose flexible service has a named quarter but no filed date, and the piece most likely to draw FERC questions. PALS also carries the most developer-friendly resource adequacy treatment in the country: it would impose no additional resource adequacy obligation on participating non-firm loads.

CAISO’s calendar is the shortest, and the thinnest. Its Flexible Interim Load Interconnection service — FILI — lets a load of 50 megawatts or more connect before its network upgrades are complete, with participating transmission owners expected to finish load studies within 60 to 90 days. CAISO requested a February 16, 2027 effective date, with settlement changes following April 30, 2028. But FILI terms are negotiated case by case with the transmission owner, and the permanent flexible option floated in an August straw proposal was dropped from the filing, deferred to 2027. The show-cause orders asked for clear and consistent tariff provisions, and a case-by-case interim service is neither.

What “speed to power” really means

Step back from the dates and the pattern is unmistakable. In every region, the fastest route to the grid runs through non-firm or curtailable service. That is the bargain the filings all strike: speed is available, firmness is not. A load that accepts curtailment can connect sooner. A load that wants firm service waits for the upgrades to be built.

The curtailment terms are the price of that speed, and they differ enough to change siting decisions. SPP’s PALS would dispatch a load to zero when the locational price exceeds a $25 per megawatt-hour bid cap — the most aggressive curtailment of the six, and the one with the least resource adequacy obligation attached. MISO’s GRITS curtails above $100 per megawatt-hour, NYISO’s non-firm service at $200, and ISO New England re-dispatches above $250, in about 1 percent of hours. PJM requires customers to cut withdrawals within five minutes. A $25 cap and a $250 cap are different businesses. The interim clocks run long — up to seven years in SPP and ISO New England — and the conversion to firm service is the moment none of these filings has yet demonstrated.

What to plan for

For a developer, the calendar breaks into three planning horizons. In 2027, the tariffs take effect — February for NYISO, MISO, CAISO, and SPP’s study and funding changes; March for PJM — and the study processes, fees, and cost recovery agreements switch on. Projects already in the queue should be reviewing transition and grandfathering provisions now: answers to the filings are due December 16, and FERC can accept a filing, accept it subject to condition, set it for hearing, or prescribe a remedy of its own. Nothing is approved.

In 2028, the services start to arrive. ISO New England’s new services begin June 1, 2028, with applications opening a year earlier. NYISO’s market rule changes take effect June 1, 2028. CAISO’s settlement changes land April 30, 2028. SPP’s PALS is targeted for the second quarter of 2028, though it has no filed date. A project that can live on non-firm service can plan a 2028 energization in several regions. A project that cannot curtail should not.

In 2029, the study cycles finish. PJM’s first combined Fast Energization cycle would not finish until 2029. MISO’s GRITS would not start until January 2029. Those are the dates for the services that do the most work: the combined study that replaces four separate clocks, and the flexible service that lets a load split firm and non-firm demand.

The queue, extended

This desk’s explainer on interconnection queues made the point that a queue is an options portfolio, not a construction pipeline — that the useful signal is not the total but the composition and the cost curve. The large-load filings extend that logic to the demand side: fees, deposits, readiness requirements, cost recovery agreements, exit fees, and minimum financial commitments are all mechanisms for pricing speculation out of the process.

The calendar is the other half of that question. A developer that can wait until 2029 is a different kind of developer from one that needs power in 2027, and the filings sort them accordingly. The fast lane is open. It is non-firm, it is curtailable, and in most regions it does not start for another year or two. The firm lane is being built.