On November 16, 2026, PJM Interconnection asked the Federal Energy Regulatory Commission to impose voltage and frequency ride-through requirements on Large Computational Loads β data centers, crypto mines, and AI campuses. The filing, in Docket No. ER27-522-000, would require those facilities to stay connected through defined transmission disturbances instead of doing what they did on July 22: disconnecting in waves and transferring thousands of megawatts to on-site backup while the fault itself was already cleared. PJM asked for a January 16, 2027 effective date and an order by January 15. Until FERC acts, it is a proposal, not a rule.
The stakes are set by scale. PJM already serves about 10 gigawatts of large computational load and forecasts additions of up to 30 gigawatts more by 2030. The ride-through filing was one of three PJM packages filed the same day: a Fast Energization proposal in Docket ER27-531 that would compress generation and large-load study timelines from two years to one, and a transmission owners’ filing in Docket ER27-520 setting rates, cost allocation, and cost recovery for large and co-located loads. The ride-through filing answers the most urgent gap in FERC’s June 18 show-cause order, and it reaches facilities already running, not only ones still in the queue.
The July morning that forced it
At 7:56 a.m. on Wednesday, July 22, a mechanical failure took a 230-kilovolt transmission line out of service in Dominion Energy’s Northern Virginia zone, home to the densest concentration of data centers on Earth. Dominion’s preliminary investigation blamed a sub-conductor that pulled free from a compression sleeve after its bolts were improperly torqued and the sleeve overheated. The fault itself was cleared normally, in two to three cycles β about 33 to 50 milliseconds. What happened next was not the grid’s doing: the data centers’ own protection systems began disconnecting their server halls and transferring them to on-site backup, without warning.
The transfer came in two waves. The first dropped 2,970 megawatts; the sudden loss of load pushed voltage up, triggering a second wave of 1,099 megawatts. PJM put the total at about 3,800 megawatts in August and about 3,900 megawatts in October slides; either way it was the largest load transfer in PJM’s history, cutting its load from 99,984 megawatts to 96,205 megawatts, roughly 3.8 percent. System frequency jumped to 60.092 hertz and local voltage peaked near 1.138 per unit. Operators restored balance within nine minutes, inside NERC’s 30-minute standard.
Operating Committee Chair Emanuel Bernabeu’s verdict on August 6 was blunt: “This was a normally cleared fault. They should not disconnect from the grid.” July 22 was the third event of its kind in two years, and each one was bigger than the last: about 1.5 gigawatts on July 10, 2024, and about 1.8 gigawatts on February 17, 2025. PJM’s David Souder called the pattern “unsustainable.” The protection equipment was doing what it was set to do β shielding sensitive equipment from voltage it disliked. But thousands of megawatts of protection acting at once had become a grid event in its own right. PJM principal engineer Byoungkon Choi told FERC that Dominion’s analysis puts most of the July 22 tripping inside the voltage envelope PJM now proposes β so the rule would likely have mitigated much of that morning’s transfers.
Who counts as a large computational load
The filing creates a new tariff category, the Large Computational Load, defined in two steps. First, the facility must be a Large Load: a cumulative peak of 50 megawatts or more at a single electrical site, a definition FERC accepted effective October 12, 2026. Second, at least 25 megawatts of the facility’s maximum load must be served through power electronic conversion equipment. That second test does the work: it separates a data center or a crypto mine from a steel mill of the same size, and it is drawn by equipment rather than end use.
PJM’s reasoning, in testimony from David Egan, its senior manager for generation modeling and dynamic studies, is that what matters is “the presence of large quantities of power electronic conversion equipment.” Server racks and GPU clusters run on solid-state rectifiers and switch-mode power supplies, with no spinning mass, no mechanical inertia, and no inherent tendency to ride through a disturbance the way a motor load does. Whether a facility stays connected through a voltage sag is decided by its settings β its uninterruptible power supplies, static transfer switches, and protection coordination. The obligation sits on the Eligible Customer taking transmission service on the load’s behalf β a utility, a power marketer, or a retail customer β and applies under network service or the new large-load services filed the same day.
What the rule requires β and where the numbers live
The key structural fact: FERC is being asked to approve an obligation, not a set of numbers. The proposed tariff language says PJM “shall establish minimum voltage ride-through and frequency ride-through requirements,” which “shall be set forth in the PJM Manuals” β specifically Manual 14B, Attachment D-2. The voltage and frequency tables PJM showed stakeholders in September and October are not in the tariff text. PJM’s transmittal letter says the manual language is “in an advanced stage of development,” and Choi’s declaration argues PJM should be able to adjust the parameters without a lengthy stakeholder process or a new FERC approval.
The draft numbers are the shape of the rule, not the rule itself. PJM’s September draft showed continuous operation between 0.90 and 1.10 per unit voltage, at least two seconds between 0.80 and 0.90, at least half a second between 0.50 and 0.80, and at least a quarter of a second below 0.50. During a sag, a site could cut its draw in proportion to the voltage drop, but would have to return to more than 90 percent of its earlier draw within two seconds of recovery. On frequency, an October 28 slide showed a continuous band of 58.8 to 61.2 hertz, with facilities holding their draw within 10 percent during swings.
The September draft also barred transfer-to-backup schemes that disconnect a load solely because of a count of voltage sags or swells where it must ride through β a direct answer to the dip-counting logic behind July 22. None of these figures is final, and that placement is where the coming fight will be: it leaves PJM free to revise the envelope without a new FERC filing. Two items from PJM’s October 28 slide are absent from the filed tariff: 90-day accelerated compliance for reliability-risk loads, and limited exceptions where requirements cannot be met. Owners of the existing 10 gigawatts have the most reason to ask FERC to pin the parameters down in the tariff itself. PJM has consented to FERC severing the ride-through rule from the rest of the package.
No exemption for the 10 gigawatts already there
The proposed tariff sorts loads into three groups. New loads, whose customers enter the study process on or after the effective date, must demonstrate compliance to interconnect and operate. Existing sites that cross the 50-megawatt line or are materially modified on or after the effective date must comply as well. Transitional loads β those whose customers had already started or completed a study, executed an interconnection agreement, started construction, or reached commercial operation β must comply within a year of the effective date or a year of commercial operation, whichever is later. At the requested date, that means January 16, 2028, at the earliest.
That breaks deliberately with the other regions that have written ride-through rules. ERCOT, which implemented ride-through requirements for large data centers and crypto mining facilities on August 1, exempted loads operating or approved before November 14, 2025. PJM’s September stakeholder deck had reproduced those exemptions without saying whether it would copy them β it will not. Choi’s declaration states the reason plainly: “unlike ERCOT and MISO, exempting existing facilities is not appropriate in PJM because the magnitude of existing computational load and its demonstrated operational impacts warrant consistent application of the requirements to both existing and new facilities.” Every documented event so far has come from existing sites; a rule exempting the 10 gigawatts already connected would have exempted the problem.
The rest of the package: ramps, telemetry, remote disconnect
Ride-through is the only obligation in the filing with draft numbers behind it. The rest is framework: tariff placeholders for ramp rates, electromagnetic transient performance, auxiliary equipment and protection systems, maintenance outage timing, remote disconnection, control technology and telemetry, and data and communications. Each will be set in the manuals after stakeholder engagement in early 2027. These are the remaining items from FERC’s June 18 show-cause order.
Remote disconnection is the other side of the ride-through coin. Ride-through tells a facility it may not take itself off the grid; remote disconnection lets the operator take it off when necessary. Together with ramp-rate limits, they would convert the largest loads from an unmanaged disturbance into a managed resource β one the operator can see through telemetry and direct through operating instructions. The filing also adds an annual transmission service reporting requirement β transparency for states tracking what large loads are served, and at whose cost.
How it fits the federal track
The filing’s procedural frame is the June 18 show-cause order, 195 FERC ΒΆ 61,211, in Docket No. EL26-67-000, which preliminarily found PJM’s tariff unjust and unreasonable for lacking operational requirements for large loads. Under FERC’s August 14 abeyance order, 196 FERC ΒΆ 61,129, a respondent that files by November 16 has its obligation to answer suspended, and the proceeding stays in abeyance. The substance now faces the answer period; FERC may accept the filing, accept it with conditions, set it for hearing, or prescribe a remedy of its own.
The filing also sits inside a second, federal track on a parallel clock. On July 16, FERC ordered in Docket No. RD26-7-000, 196 FERC ΒΆ 61,031, that NERC file new or modified reliability standards for computational-load integration by December 31, 2026, revised Rules of Procedure by the same date, and a March 1, 2027 informational filing on the next phase. On October 15, NERC’s stakeholders approved three new standards β CLO-001-1 on interconnection studies and modeling, CLO-002-1 on operations and communications, CLO-003-1 on protection coordination and disturbance monitoring β and the package now goes to the NERC board for adoption this quarter.
But as this desk noted, the NERC package sets no industry-wide minimum voltage and frequency ride-through requirements. It requires modeling data on ride-through capabilities, without saying what disturbances every qualifying facility must ride through. That gap is what PJM’s filing fills for its own footprint: a federal floor, with the big grid operators writing the detailed performance rules on top. The performance rules are being written while the governed load is still arriving.
What compliance will cost
PJM’s filing contains no cost estimate for compliance, and no per-megawatt figure has been published β an absence worth stating plainly. The cost falls into three buckets of very different sizes. The cheapest is a settings change: retuning uninterruptible power supplies, static transfer switches, and protection coordination so a facility rides through a sag. The expensive cases are sites whose UPS or transfer equipment cannot be retuned to the envelope and needs hardware replacement. The third bucket is ongoing: modeling data kept current as servers are swapped and firmware updated, commissioning tests, telemetry, and disturbance recording.
The burden will not land evenly. Hyperscalers with standardized designs and in-house power engineering can retune a fleet from a central template; smaller operators and multitenant facilities face a harder problem, because the facility operator may not control tenants’ equipment. The obligation sits on the Eligible Customer taking transmission service, but the work and cost will flow through to the facility owner and, in multitenant buildings, to the tenants whose settings are at issue. Until the manual numbers are final, no owner can price the work precisely β one reason comments will press FERC to pin down the envelope.
What to watch
Four things will decide what this filing means in retrospect. First, FERC’s action: PJM asked for an order by January 15, 2027, and the answer period will test whether the Commission accepts the obligation-and-manuals structure, conditions it, or sets it for hearing. Second, the manuals, where the draft voltage curve and the 58.8-to-61.2-hertz band either survive or change β and whether the 90-day acceleration and limited exceptions reappear. Third, the companion filings: Fast Energization in ER27-531, which would connect new loads in half the time, and the transmission owners’ cost-recovery package in ER27-520, which decides who pays for the wires.
The fourth test is one no docket schedules. The next normally cleared fault in Northern Virginia will show whether the load stays on the grid β and whether a year of settings changes, commissioning tests, and manual language has changed what thousands of megawatts of protection equipment does in 50 milliseconds. July 22 proved that a fault the grid clears cleanly can still become a grid event when the load on the other end of it decides to leave. PJM’s filing is the grid’s answer: the decision to leave is no longer the facility’s alone.