Today is the day the letter set. On November 18, eight ratepayer-advocate offices in seven states wrote to PJM Interconnection’s Board of Managers, asking it to direct the grid operator to seek Federal Energy Regulatory Commission approval to postpone the Base Residual Auction for the 2029/30 delivery year, scheduled to open December 9 and close December 15. They asked for a written answer by November 23. As of this morning, there is no public answer. The auction is sixteen days from opening. Silence is itself an answer: a board that misses its own deadline has told the market the auction will run.
The second thing that was supposed to happen before today also did not visibly happen. The advocates’ letter noted that PJM planned to publish final planning parameters on November 19 that could remove canceled or delayed data-center projects from the demand curve. As of this morning, PJM’s own capacity market page still lists the 2029/30 planning parameters report dated October 29. No revised parameters document dated November 19 is posted, so nothing in the record shows the forecast was trimmed.
The parameters that changed nothing anyone can see
Planning parameters are the numbers PJM publishes before each auction: the reliability requirement, the forecast peak load, the demand curve, and the price collar. For the 2029/30 auction they set a reliability requirement of 158,712 MW, a forecast peak load of 171,916 MW — up 5,963 MW, or 3.6 percent, from the 2028/29 auction — and a collar capped at $337.83 per MW-day with a floor of $181.91. The monitor’s finding is that the demand curve still includes more than 20,000 MW of forecast data-center load. Of the forecast increase in data-center load between the 2026/27 and 2028/29 delivery years, 4,017 MW — 42 percent — had been canceled or delayed as of September 21.
The November 19 date mattered because it was the last plausible moment to fix that. The advocates wrote that the final parameters “may remove canceled or delayed data center projects from the auction’s demand curve” — and then said, in the same paragraph, that even that would not be enough. Removing canceled projects is a data update: the forecast gets newer, and the requirement falls by however many megawatts the update catches. What the monitor recommends is a rule change: forecast data-center load — real, speculative, and canceled alike — comes out of the capacity auction entirely, and is procured through a separate mechanism. A refresh can only catch projects that have already failed; the rule change addresses those that have not failed yet, and may never be built.
The absence matters less than it might seem, and also more. Less, because the advocates had already said a refresh would not satisfy the monitor’s recommendation. More, because revised parameters would at least have let PJM argue the auction prices a cleaned-up number. The auction will run against the October parameters, and the monitor’s estimate — that it clears at the $337.83 cap and adds another $5 billion to $10 billion in data-center-related costs — is the only quantitative forecast of the result in the public record. PJM has not published a competing estimate.
PJM spokesman Jeffrey Shields told Utility Dive the cap is “an important safeguard against how high prices can rise” and postponing “could destabilize the market and increase the risk of power interruptions when customers need electricity most.” The cap argument is half true. The cap bounds the price — no megawatt can clear above $337.83 per MW-day — but not the quantity, and the quantity is where the money is. At the reliability requirement of 158,712 MW, clearing at the cap implies a total auction cost on the order of $19.6 billion over the delivery year. The July auction cleared at its $325 cap in every zone and still came up 6,831 MW short, procuring 138,318 MW of unforced capacity. A cap that is hit is the price of the auction, not a safeguard against an expensive one.
Why a forecast refresh was never the ask
The advocates’ letter quotes the monitor’s recommendation as a structural one: “to fundamentally change how forecasted data-center demand is treated in the capacity auction so that existing consumers are not required to subsidize speculative or uncommitted data center demand.” The monitor’s case, in its November 12 State of the Market report, is not that PJM’s forecasters made an arithmetic error. It is that a three-year-forward auction cannot price a forecast of data-center load without systematically overbuying: the forecast is built from developer announcements and utility large-load adjustments, with no mechanism to true up when the announcements do not materialize.
Including existing and forecast data-center load has already increased capacity costs by $29.4 billion across the four Base Residual Auctions already run, for the 2025/2026 through 2028/2029 delivery years — 46.2 percent of the $63.6 billion in total capacity charges. In the most recent auction alone, for 2028/2029, the monitor estimates $6.3 billion of $16.4 billion in charges was a result of data-center load. The monitor calls the $29.4 billion irreversible: those auctions have cleared, and no forecast revision can claw any of it back.
In the first nine months of 2026, data-center load lifted the average wholesale power price by $9.95 per MWh, or 9.8 percent, to $111.61 per MWh — the capacity-market effect only. PJM disputes the $29.4 billion figure, saying the monitor’s total “does not equate to the total cost to load”: a change in auction revenues is not the same as a change in what customers ultimately pay, given hedging, rate cases, and allocation rules. That objection is fair as far as it goes. The monitor’s figure is a counterfactual — what capacity revenues would have been without data-center load in the demand curve.
If data-center load had stayed at the level forecast for the 2026/2027 auction — 11,993 MW instead of 21,474 MW — the July auction would have produced a 1,096.5 MW surplus rather than a 6,831.3 MW shortfall. If only the 4,016.9 MW of canceled or delayed load is treated as never arriving, the shortfall falls to 3,055.0 MW, a 55 percent reduction. The shortfall is highly sensitive to a forecast that has already moved by more than 4,000 MW. Not all of the forecast is phantom, either: trade coverage citing Cleanview data showed developers began construction in the third quarter on 8.4 GW of data-center capacity at 65 buildings. The monitor’s case is not that data centers are imaginary: the forecast includes projects at every stage from breaking ground to a press release, with no discount for the difference.
The board’s three options, and the one it cannot take alone
What can the board actually do? The answer is narrower than the letter’s language suggests. The board cannot postpone the auction: only FERC can move a scheduled auction, because the auction calendar is in PJM’s tariff. What the board can do is direct PJM staff to seek FERC approval to postpone — a filing asking the Commission for a waiver of the tariff’s auction schedule, which FERC could grant, deny, or sit on.
The board’s realistic options are three. First, it can direct the filing, putting the question to FERC with sixteen days before the auction opens and almost certainly drawing immediate intervention from generators, load-serving entities, and the states that did not sign the letter. Second, it can decline, in writing or by silence, leaving the auction on schedule and the letter as a record. Third, it can answer in a way that neither directs nor declines — acknowledging the concern and deferring the structural question to the tariff process. That third option is the most likely, and the least satisfying to either side.
The board also has a political constraint the letter does not name but that shapes everything about it. The January “statement of principles” endorsed by PJM and the governors of its 13 states emphasized that large-load forecasts must be “real and verified.” That was a political document, not a tariff rule, but the advocates are using it as PJM’s own standard. Proceeding with an auction that prices speculative data-center demand, the letter says, “would undermine that commitment and expose consumers to billions in potentially avoidable costs.” The board cannot easily say the principles do not apply to the December auction.
If the board says no — or says nothing
The most likely outcome, on the evidence available this morning, is that the auction opens December 9 on schedule. PJM’s spokesman has already said, in substance, that the grid operator will not seek a delay: the system urgently needs capacity, and postponing this close to execution could destabilize the market. That is a staff position, not a board answer, but boards rarely overrule their staff on a sixteen-day clock without a public fight, and there has been none.
If the auction runs, the consequences are the ones the monitor has already priced. The auction is the fourth and final one under the price collar, and the monitor’s expectation is that it clears at the $337.83 cap. The results post December 22. The $29.4 billion grows by whatever the December clearing adds. The advocates’ letter becomes a record — evidence for the FERC proceedings that follow.
There is also a second consequence, and it is the one PJM’s spokesman is actually warning about. The July auction’s 6,831 MW shortfall is a real reliability gap, not a forecast artifact. Postponing an auction does not postpone the load — it postpones the procurement. The advocates’ answer is the backstop: a separate reliability procurement for the large loads. But the backstop is not ready, and that is the letter’s weakest flank. FERC accepted the backstop filing on September 29 and suspended it until February 28, 2027, pending a paper hearing. PJM refiled on October 29 with a far smaller target — roughly 630 MW, by the latest estimates — after utility forecast revisions shrank the gap; its bid window is March 1–28, 2027, with results in May. The backstop exists because the July auction failed, it is delayed because FERC suspended it, and the December auction runs with the forecast load in it because the backstop is not there.
The parallel clocks
The letter is not the only instrument running against the December auction. Exelon’s November 3 complaint at FERC, docketed as EL27-11, challenges the three-year-forward auction schedule partly over the uncertainty in forecasting data-center load, and asks the Commission to order PJM to move to a prompt capacity auction held two months before the delivery year, starting with the 2030/31 delivery year, and to rule by January 31. Exelon wants to shorten the horizon so the forecast has less time to be wrong; the advocates want to delay this auction so the forecast can be corrected before it is priced.
A third clock started last week. On November 16, PJM filed its tariff proposal responding to FERC’s June show-cause orders on large loads. The large-load rules will shape how data-center load is treated for years, but they will not touch the December auction, which runs under the tariff as it stands. That is the pattern of this whole dispute: every durable fix is on a clock that runs past the auction, and the auction is the one event that cannot wait. The fourth clock is the redesign: on November 13, PJM convened a workshop on more than 30 papers responding to its May white paper, which offered three broad pathways and recommended none — a multi-year project by PJM’s own timeline. The December auction closes in three weeks. The monitor’s report does not resolve that mismatch. It prices it: another $5 billion to $10 billion, on the monitor’s estimate.
What to watch
Today, November 23, is the first date. If the board answers in writing, the answer will show whether the letter is treated as a governance question or a stakeholder comment. If it does not answer today, the silence will have to be read the same way: the advocates asked for a written response by November 23, and a board that lets the date pass without one has answered anyway. Either way, the answer should be read alongside the planning parameters, or their absence: declining a delay while pointing to a cleaned-up forecast is a different argument than declining one while the October parameters stand unchanged.
December 9 is the second date, and it is the one that decides the matter. If the auction opens on schedule, the letter becomes a record, and the argument moves to FERC — to Exelon’s complaint, to the backstop’s paper hearing, and to the redesign. The results, due December 22, will be read as evidence in every one of those proceedings. The three numbers to read first are the clearing price, the shortfall against the 158,712 MW requirement, and the data-center load in the demand curve. The fourth thing to watch is whether PJM publishes anything further on the November 19 parameters before the auction opens. The forecast is the fight now. The auction is only where it gets priced — and as of today, nobody has said the price will differ from the one the monitor predicted.