A tenth of a megawatt is now the most consequential distance in the Texas power market. At 75 MW, a data center enters ERCOT’s large-load review, posts financial security, and waits in the Batch Zero study that has been frozen since August. At 74.9 MW, it can work directly with its local utility and skip that review altogether. On November 5, ERCOT told the Public Utility Commission of Texas that it has noticed how many projects are choosing the second side of that line.

The briefing, by Chad Seely, ERCOT’s senior vice president of regulatory policy, general counsel and chief compliance officer, was reported by the San Antonio Express-News on November 6. Seely told commissioners that nearly 10 GW of medium-size loads โ€” 25 MW to just under 75 MW โ€” were working with utilities to connect, concentrated between 60 and 74.9 MW. ERCOT has sent 132 requests for information to transmission and distribution service providers, asking for each project’s size, location and planned energization date, to work out whether developers downsized to stay under the line. The account gave no count of projects in the 60 to 74.9 MW band, and no figure for the megawatts in that band alone has been published. The cluster is real; its total size is not yet known.

One correction is worth making at the start. The threshold inquiry is not the Batch Zero audit, and it is not a part of it. The Batch Zero audit is the verification of large loads of 75 MW and above ordered by Governor Greg Abbott on August 3, with reports due December 10. The sub-75 MW inquiry is a separate workstream running alongside it, aimed at loads ERCOT’s large-load process does not study at all. ERCOT is auditing the queue it can see, and now it is also counting the load it cannot.

The number that frames the cluster

Start with the scale. ERCOT was tracking about 474 GW of large-load interconnection requests as of June 2026, up from about 63 GW at the end of 2024, with roughly 90 percent from data centers. That is a queue of requests, not a demand forecast. Against it, ERCOT set a preliminary all-time peak demand record of 91,134 MW on July 22, 2026 โ€” the queue asked for more than five times the power the state has ever used at once.

The load actually running is a small fraction of either figure: ERCOT’s September 2026 Monthly Operational Overview counted 9,456 MW of large loads approved to energize, and the sum of those loads’ individual monthly peaks in September was about 4,132 MW โ€” a sum of non-simultaneous peaks, not a single coincident moment. The medium-size total Seely cited โ€” nearly 10 GW โ€” is larger than that approved figure, and larger than the 6,608 MW carried by the 17 loads frozen pending the December 10 audit. A category designed to be the smaller end of the process now holds as much demand as the energized large-load fleet.

The second thing the briefing established is the shape of the category. ERCOT’s community-impact survey, summarised at the same November 5 meeting, found 143 of the 429 loads in its reviewed dataset in the 50 to 75 MW band, carrying 9.8 GW โ€” the most populous band, a third of all respondents. ERCOT said more than 85 percent of the roughly 11 GW of medium-load capacity in that survey sits above 50 MW. The 60 to 74.9 MW concentration Seely described is the upper end of that band, pressed against the threshold. A distribution spread evenly across 25 to 75 MW would not look like this. The load is bunched at the top, and the top is the line.

What 75 MW buys, and what 74.9 avoids

The line was not drawn casually. Senate Bill 6, passed in 2025, directed the commission to set interconnection standards for large loads, and set the demand threshold at 75 MW unless the commission determines a lower threshold is necessary โ€” to support business development while minimising stranded infrastructure costs and maintaining reliability. The implementing rule, 16 TAC ยง25.194, was adopted September 18 and took effect October 8, and applies to a new or expanded interconnection of 75 MW or more of total expected non-coincident peak demand at a single site.

Crossing the line carries a price that is easy to calculate. A large load pays a $100,000 study fee and posts $50,000 per MW in financial security before ERCOT will study it โ€” $3.75 million at exactly 75 MW, before any allocated upgrade costs. At 74.9 MW, under the rule as written, neither applies, and the project is not studied in Batch Zero. The saving is not only money. It is time: Batch Zero is frozen, its study will not meet its original April 9, 2027 delivery date, and no new large load can be approved to energize until the audit is complete. A project at 74.9 MW avoids the freeze as well as the fee.

That is the incentive structure, and it does not by itself prove that any particular project was downsized. There are legitimate reasons to build a 70 MW data center: a tenant may need 70 MW, a site may have 70 MW of available distribution capacity, a developer may be phasing a campus at a size the local wires can carry today. The Express-News account says ERCOT is investigating whether developers reduced proposed sizes to stay below the threshold. It does not say ERCOT has found that any did, and no developer has been named. The 132 requests are the investigation, not its conclusion.

What the requests can establish is narrower than the question they pose. Size, location and energization date can show a pattern; they cannot show why a developer chose a size. That would take site-control documents, equipment orders and ownership records โ€” the evidence ERCOT’s second round of Batch Zero verification questions asks of about 80 percent of the developers in that audit. The medium-load inquiry, addressed to utilities rather than developers, asks for less.

The corroboration from Houston

The pattern did not first appear in November. CenterPoint Energy, which runs the grid around Houston, told investors on its second-quarter earnings call in July that it was already seeing 500 MW of distribution-related requests just below the 75 MW threshold, from advanced manufacturing, distributed inference data centers, and energy and logistics customers: below 75 MW, a load request does not necessarily need to go to Batch Zero. By October, CenterPoint said it had received nearly 1 GW of distribution-level load requests over the past year, without splitting out the data-center share. That is not proof of downsizing, but it shows the threshold was already shaping where load was filed months before ERCOT briefed the commission.

Why the grid operator cares even if nobody cheated

Here is the point that survives even if every 74.9 MW project was sized for honest reasons. Two 70 MW sites served by the same part of the grid add 140 MW of demand, more than a single 100 MW campus that receives an individual large-load review. The threshold is drawn per site, per project. The grid feels load in aggregate, by corridor and by substation, not by filing. A threshold that sorts projects one at a time will always miss load that arrives many at a time, just under the line.

ERCOT’s stated concern, as described in the filing that accompanied the November 5 update, is allocation. Capacity taken up by medium loads could be the same capacity already allocated to base load in Batch Zero, leaving little room for native load growth. The September study conditionally included 362 projects totalling about 194.3 GW and excluded 373 totalling about 302 GW. If medium loads connect through utilities and consume capacity the study assumed was available, the study’s arithmetic is wrong in a way no audit of the large loads themselves can fix.

What ERCOT can actually do about it

The remedies available to ERCOT are narrower than the problem. A project below 75 MW was never in Batch Zero, so it cannot be disqualified from Batch Zero; the audit’s sanction does not reach it. The medium-load findings are expected to be published with the commission on or before December 10, but ERCOT has not said what form they will take, or whether they will name projects.

What Seely did say is that the findings could prompt the commission to consider requirements for loads below 75 MW. That has a statutory hook: Senate Bill 6 lets the commission set a lower threshold if it determines one is necessary. Lowering it to 50 MW, or to 25 MW, would bring the crowded band inside the review process โ€” and hundreds of projects currently proceeding through utilities with it. None of the rule, study process or queue that would require exists today for medium loads, and none of it can be created by December 10.

A second option is disclosure rather than review: requiring utilities to report medium-load requests to ERCOT as they arrive, so the grid operator can see the aggregate even if it does not study each project. A third is aggregation: treating multiple sub-threshold projects at a single site, or under common ownership, as one load. The large-load rule already tests total expected peak demand at a single site and requires disclosure of similar requests elsewhere in Texas, which limits the simplest form of splitting a campus โ€” though whether it reaches nominally separate sites filed by affiliated developers is a question the 132 requests were designed to surface.

The fourth option is already in motion: the December 31 cost-allocation deadline in Project No. 58000. The commission’s proposal would replace the four coincident peak methodology with a twelve coincident peak methodology and create a take-or-pay transmission rate for customers above 75 MW, allocating costs on contracted capacity for two decades. If that lands as proposed, a large load pays for the wires built for it whether or not it uses them โ€” which makes the sub-75 MW route more attractive, not less, unless the commission extends a similar obligation downward. The threshold and the cost rule are pulling in opposite directions, and December will decide both.

What it means for the market

For a developer, the November 5 briefing changed the risk calculation without changing any rule. A project sized at 74.9 MW today may be inside a review process tomorrow, and may face a transmission obligation it did not price โ€” whether it sized honestly for a tenant’s actual need or not, because any remedy will be drawn by size, not by motive. That is the cost of building on a bright line: the line can move, and when it moves it moves for everyone on it.

For a buyer of power, the sub-75 MW cluster is a second source of schedule risk, alongside the freeze. A data center’s energization date was already a regulatory date, set by an audit report and a commission meeting rather than by a construction schedule. A campus energizing in phases, each under 75 MW, now has to price the possibility that a later phase is reclassified. Power purchase agreements priced on energization dates carry schedule risk no hedge covers, because the hedge settles on price and the delay is in time. For everyone else in ERCOT, the question is who pays for the wires the medium loads will use: under the current allocation, that cost lands substantially on existing customers, and medium loads post no $50,000-per-MW security and face no take-or-pay obligation.

What to watch

December 10: the two Batch Zero reports, and whatever ERCOT publishes alongside them on medium loads. Read the medium-load findings for three things: how many projects the 132 requests turned up, what share sit in the 60 to 74.9 MW band, and whether ERCOT names a mechanism โ€” a lower threshold, a disclosure duty, an aggregation rule โ€” or only a concern. A count without a remedy is a description; a remedy without a count is a guess.

December 17 and December 31: the commission’s open meeting, the earliest the audit can be treated as complete, and the statutory deadline for the Project 58000 rule amendments. Watch whether commissioners direct staff to open a rulemaking on loads below 75 MW, and whether the final cost-allocation rule keeps take-or-pay for loads above 75 MW while saying anything at all about loads below it. A rule that makes large loads pay for their wires, while leaving medium loads outside the obligation, does not close the gap. It prices it.

The 75 MW line was drawn to separate projects that need system-level study from those that do not. The November 5 briefing says the market has learned to build right up against it, in numbers large enough to matter to transmission planning. The question is whether a threshold designed for a different era of load growth can survive when the marginal megawatt is worth millions โ€” and whether the state, having found the load it was not studying, decides to study it, or only to count it.