On Wednesday, eight ratepayer-advocate offices in seven states wrote to the PJM Interconnection board and asked it to do the one thing the grid operator has been unwilling to do all year: stop. Postpone the 2029/30 Base Residual Auction, scheduled to open December 9 and close December 15, until data-center loads — “both real and speculative” — can be removed from the load forecast, and hold a separate reliability backstop procurement for the large loads instead. They want a written answer from the board by November 23.

The letter is not a new argument. It is the market monitor’s argument, now carrying the signatures of the people whose constituents pay the bill. On November 12, Monitoring Analytics, PJM’s independent market monitor, released its quarterly State of the Market report for January through September and recommended postponing the December auction, warning that PJM’s forecast includes data centers that have been canceled or are unlikely to reach their projected demand — and that pricing that phantom load could impose an additional $5 billion to $10 billion on PJM’s 67 million consumers. The advocates’ letter cites that report directly, and treats the monitor’s warning as the basis for a formal request that the board direct PJM to seek Federal Energy Regulatory Commission approval to move the auction. PJM would need that approval to delay; it cannot move a scheduled auction on its own.

That is the shape of the dispute now. The December auction is no longer a debate about whether the price is too high. It is a debate about whether the demand the auction prices is real.

What the monitor actually found

Start with the two numbers that frame everything else, because they are the monitor’s numbers, not anyone’s rhetoric. The first is backward-looking: including existing and forecast data-center load in the capacity market has already increased capacity costs by $29.4 billion for all customers, according to the November 12 report — the cumulative effect across the four Base Residual Auctions already run, for the 2025/2026 through 2028/2029 delivery years. The monitor calls that increase irreversible, and it is: those auctions have cleared, the commitments have been made, and the money is on the bill.

The second number is forward-looking, and it is the one the letter is about. The monitor estimates that leaving forecast data-center load in the December auction “effectively ensures that the auction will clear at the maximum price and add another $5 to $10 billion of data center related costs to all customers.” That is an estimate, not a result, and it is contingent on two things: the load staying in the forecast, and the auction clearing at the cap. Both conditions are likely on the current trajectory — the July auction for 2028/29 cleared at the $325 per MW-day cap in every zone and still came up 6,831 MW short — but neither is certain, and the range is the monitor’s, not PJM’s and not the advocates'.

The mechanism is straightforward, and it is the same mechanism this desk has described since the summer. A capacity auction buys a reliability requirement — a quantity of megawatts deemed necessary to keep the lights on — and the price is set by where the supply curve meets that requirement. When the requirement is inflated by load that will not materialize, the auction buys more capacity than the system needs, and because supply is short, it buys it at the highest price the rules allow. The December auction is the fourth and final auction under the price collar, capped at $337.83 per MW-day with a floor of $181.91, against a reliability requirement of 158,712 MW — 2,699 MW higher than the year before — and a forecast peak load of 171,916 MW, up 5,963 MW, or 3.6 percent, from the 2028/29 auction. The monitor’s finding, as this desk reported last week, is that the demand curve still includes more than 20,000 MW of forecast data-center load.

The load figure is the contested part. The monitor has documented that 4,017 MW — 42 percent — of the forecast increase in data-center load between the 2026/27 and 2028/29 delivery years had been canceled or delayed as of September 21. That is a measured cancellation rate, not a suspicion. The question the letter poses is what share of the remaining forecast is real, and who bears the cost of guessing wrong.

Eight offices, seven states

The signatories are the Office of the Ohio Consumers’ Counsel, the Delaware Public Advocate, the West Virginia Consumer Advocate, the Maryland Office of People’s Counsel, the Pennsylvania Office of Consumer Advocate, the New Jersey Division of Rate Counsel, the Illinois Attorney General’s Office, and the Illinois Citizens Utility Board — eight offices covering seven states. Their letter is addressed to the PJM board, not to FERC, because the board is the body that would have to direct the grid operator to seek the delay.

The letter’s framing anticipates the objection PJM has already made. The advocates note that PJM was to publish final planning parameters for the auction on November 19 — parameters that could remove canceled or delayed data-center projects from the demand curve — and then say that even a cleaned-up forecast would not satisfy the monitor’s recommendation. The monitor’s recommendation, they write, “is to fundamentally change how forecasted data-center demand is treated in the capacity auction so that existing consumers are not required to subsidize speculative or uncommitted data center demand.” The delay, in their framing, “would allow PJM to implement the IMM recommendations, subject to FERC approval and appropriate reliability safeguards.” Whether the November 19 parameters actually trim the forecast was not yet publicly clear at the time of writing.

The advocates also reach back to a commitment PJM itself made. A “statement of principles” endorsed in January by PJM and the governors of its 13 states emphasized that large-load forecasts must be “real and verified,” the letter says — and proceeding with an auction that incorporates speculative data-center demand “would undermine that commitment and expose consumers to billions in potentially avoidable costs.” The January principles were a political document, not a tariff rule, but the advocates are using them as PJM’s own standard — and asking the board to measure the December auction against it.

PJM’s answer, so far

PJM’s response, delivered by spokesman Jeffrey Shields to Utility Dive, is the position the grid operator has held since the price spike began: the cap is the safeguard, the demand is real, and delay is the risk. “The December auction includes an established price cap, providing an important safeguard against how high prices can rise,” Shields said. “The system urgently needs capacity to meet rising demand. Postponing the auction this close to its execution could destabilize the market and increase the risk of power interruptions when customers need electricity most.”

The demand claim is the one the monitor disputes, and it is the heart of the matter. “Electricity demand is growing faster than new power supplies can be built,” Shields said, and “PJM must plan for the demand those decisions create.” That is true of real demand. The monitor’s finding is that a measurable share of the forecast is not real demand — it is canceled projects and unlikely projections — and that planning for it as though it were real is what produces the $5–10 billion estimate. PJM’s statement does not engage that distinction; it treats the forecast as the demand. That is precisely the treatment the advocates’ letter asks the board to reconsider. And the cap, for all its force, bounds the price, not the quantity: at the reliability requirement of 158,712 MW, even the cap implies a total auction cost on the order of $19.6 billion over the delivery year. A safeguard against high prices is not a safeguard against unnecessary purchases.

The destabilization claim is the strongest argument for proceeding, and it should not be dismissed. An auction scheduled to open December 9, with results posted December 22, is nineteen days from opening; market participants have positioned supply, credit, and hedging around that schedule. Moving it requires FERC approval and a new schedule — and the backstop itself is suspended until February 28, 2027, pending a paper hearing at FERC, after the Commission accepted the Large Load Registry in its October 9 order and rejected the curtailment and bring-your-own-capacity frameworks. A delay is not a pause button. It is a new proceeding, on a clock that runs through the winter.

The backstop that isn’t ready

That is the letter’s weakest flank, and PJM knows it. The advocates ask for a separate reliability backstop procurement for the large loads — the mechanism PJM designed for exactly this purpose, a one-time 15-year contracting channel for the capacity the July auction failed to procure. But the backstop, as the monitor itself noted, has been pushed back and will not happen before the December auction. That timing is the monitor’s own argument for postponement: forecast load stays in the demand curve because the alternative procurement is not there yet. The circularity is the story — the backstop exists because the July auction failed, it is delayed because FERC suspended it, and the December auction runs with the forecast load in it because the backstop is not there. The advocates ask the board to break the circle by moving the auction. PJM’s response is that moving the auction breaks the market’s schedule instead.

Exelon’s complaint, and the second clock

The advocates’ letter does not arrive alone. It cites Exelon’s November 3 complaint at FERC, which challenged the three-year-forward auction schedule partly over the uncertainty in forecasting data-center load and the resulting billions in potential excess capacity costs. Exelon’s complaint, docketed as EL27-11, asks FERC to order PJM to move to a prompt capacity auction held two months before the delivery year, starting with the 2030/31 delivery year, and asks the Commission to rule by January 31.

The complaint and the letter are different instruments aimed at the same diagnosis, and they pull in the same direction on the forecast question while diverging on the remedy. Exelon wants to shorten the horizon so the forecast has less time to be wrong. The advocates want to delay this auction so the forecast can be corrected before it is priced. Both assume the forecast is the problem. Neither, on its own, changes how forecast load is treated in the auction — which is the structural change the letter says the monitor actually recommends. And both run alongside the November 13 workshop’s three redesign pathways, which are multi-year projects by PJM’s own timeline: the letter is, in effect, a request to stop the clock on the auction the redesign cannot reach in time.

The affordability context

The letter lands in a political moment that did not exist when the July auction cleared. The request comes amid nationwide concern about electricity affordability and data centers, reflected in the midterm elections. In PJM, that concern has been driven by the recent spike in capacity prices caused by growing data-center load forecasts.

That is what turns a technical argument into a political one. The capacity market socializes the cost of the forecast across all customers: the price of procuring capacity for speculative load is spread over the 67 million people in PJM’s footprint, including households that will never use a data center’s power. The backstop and the bilateral-contracting plan are both attempts to change that allocation — to make the load that creates the cost pay for it. Until either is in place, every auction that prices forecast data-center load is a transfer, and the monitor’s $29.4 billion is the measure of how large the transfer has already been. None of that makes the delay costless: the July auction’s 6,831 MW shortfall is a real reliability gap, not a forecast artifact, and postponing an auction does not postpone the load — it postpones the procurement.

What to watch

November 23 is the first date. The advocates asked for a written board response by then, and the board’s answer — whether it engages the monitor’s recommendation, defers to PJM staff, or declines — will show whether the letter is treated as a governance question or a stakeholder comment. A board that does not answer by the 23rd will have answered anyway.

December 9 is the second date, and it is the one that decides the matter. If the auction opens on schedule, the letter becomes a record — evidence for the FERC proceedings that follow, and for the redesign that follows those. If it does not open, the question becomes what replaces it, on what schedule, and under what FERC authority. Either way, the results, due December 22, will be read as evidence in every argument the November 13 workshop produced, and in Exelon’s complaint, and in the backstop’s paper hearing. The third thing to watch is the November 19 planning parameters themselves — whether they remove canceled or delayed data-center projects from the demand curve, and by how much. The forecast is the fight now, in either case. The auction is only where it gets priced.