The deadline passed on Monday, and nothing arrived. On November 18, eight ratepayer-advocate offices in seven states wrote to PJM Interconnection’s Board of Managers, asking it to direct the grid operator to seek Federal Energy Regulatory Commission approval to postpone the Base Residual Auction for the 2029/30 delivery year, scheduled to open December 9 and close December 15. They asked for a written answer by November 23. As of November 24, no published answer from the board could be found, and nothing has appeared since. The auction opens in fourteen days; silence is now the story, and the calendar is doing the board’s work for it.

The second thing that was supposed to happen before the deadline also remains unclear. The final planning parameters PJM had said it would publish on November 19 could have removed canceled or delayed data-center projects from the demand curve; this desk found no revised parameters document dated November 19 on PJM’s capacity market page on Monday, and two days later the picture has not clarified — one secondary account describes the final parameters as published on November 19, another reports that it could not locate them. The numbers in the public record are unchanged: the reliability requirement stands at 158,712 MW, the forecast peak load at 171,916 MW, and the collar at a $337.83 per MW-day cap with a $181.91 floor.

That leaves the advocates’ letter in the same place it was on Monday, except that the clock has moved. A board that answers late can still answer. A board that does not answer before December 9 has not needed to: the auction opens on schedule, and the letter becomes a record. The question is no longer whether the board will answer by its deadline. It is what, if anything, happens in the fourteen days between now and the opening — and who, if anyone, can still move the auction.

The narrowing calendar

Fourteen days is not much time in a regulatory proceeding, and it is less than it looks. The board cannot postpone the auction itself: only FERC can move a scheduled auction, because the auction calendar is in PJM’s tariff. What the board can do is direct PJM staff to seek FERC approval — a filing asking the Commission for a waiver of the tariff’s auction schedule, which FERC could grant, deny, or sit on. Any such filing would now land with less than two weeks before the auction opens, and would almost certainly draw immediate intervention from generators, load-serving entities, and the states that did not sign the letter.

The alternative off-ramp does not run through the board at all. The advocates themselves can go to FERC. Both the Ohio and Maryland offices have said they are weighing action at the Commission if the board declines, and a filing from the states — a complaint, or a request for emergency relief — would put the same question before FERC without waiting for PJM to ask it. That is the path the silence makes more likely: a board that will not answer its own deadline in writing is not a board that is about to direct a filing on a fourteen-day clock. If the auction is to move, the states will probably have to move it themselves, and they will have to do it fast.

There is a third possibility: the board answers in a way that neither directs nor declines — acknowledging the concern and deferring the structural question to the tariff process. That answer, if it comes now, arrives after the deadline it was asked to meet, and it changes nothing about December 9.

What the auction will price

The numbers the auction will price have not moved since the monitor’s report. Monitoring Analytics, PJM’s independent market monitor, recommended in its November 12 State of the Market report that the December auction be postponed until forecast data-center load is removed from the procurement entirely, and procured instead through a separate mechanism. Its estimate is that leaving the load in “effectively ensures that the auction will clear at the maximum price and add another $5 billion to $10 billion of data center related costs to all customers.” That is an estimate, not a result, contingent on the load staying in the forecast and the auction clearing at the cap. Both conditions are likely — the July auction for 2028/29 cleared at its $325 per MW-day cap in every zone and still came up 6,831 MW short — but neither is certain, and the range is the monitor’s, not PJM’s and not the advocates'.

The backward-looking number is the one that gives the estimate its weight. Including existing and forecast data-center load has already increased capacity costs by $29.4 billion across the four Base Residual Auctions already run, for the 2025/2026 through 2028/2029 delivery years — 46.2 percent of the $63.6 billion in total capacity charges. In the most recent auction alone, for 2028/2029, the monitor estimates $6.3 billion of $16.4 billion in charges was a result of data-center load. The monitor calls the $29.4 billion irreversible: those auctions have cleared, and no forecast revision can claw any of it back.

The mechanism is the one this desk has described since the summer: when the reliability requirement is inflated by load that will not materialize, the auction buys more capacity than the system needs, and because supply is short, it buys it at the highest price the rules allow. The December auction is the fourth and final one under the price collar, and the monitor’s finding is that the demand curve still includes more than 20,000 MW of forecast data-center load.

The load figure is the contested part. The monitor has documented that 4,017 MW — 42 percent — of the forecast increase in data-center load between the 2026/27 and 2028/29 delivery years had been canceled or delayed as of September 21. If data-center load had stayed at the level forecast for the 2026/2027 auction — 11,993 MW instead of 21,474 MW — the July auction would have produced a 1,096.5 MW surplus rather than a 6,831.3 MW shortfall; if only the canceled or delayed load is treated as never arriving, the shortfall falls to 3,055.0 MW, a 55 percent reduction. Not all of the forecast is phantom: trade coverage citing Cleanview data showed developers began construction in the third quarter on 8.4 GW of data-center capacity at 65 buildings. The monitor’s case is not that data centers are imaginary — the forecast includes projects at every stage from breaking ground to a press release, with no discount for the difference.

The bill the auction sits on

The capacity argument does not arrive on a clean bill. In the first nine months of 2026, the total cost of wholesale power rose 40.9 percent, to $111.61 per MWh, from $79.19 in the same period of 2025. The monitor’s counterfactual makes the capacity share concrete: without data-center load and its impact on capacity costs for the 2025/2026 and 2026/2027 delivery years, the total would have been $101.66 per MWh — a $9.95 per MWh adder, or 9.8 percent, covering the capacity market only. Wholesale costs are not retail bills, but a 40.9 percent increase moves through, on a lag, into the rate cases that set retail rates. Maryland People’s Counsel David Lapp put it in the plainest terms available in his office’s release: “It is common sense that ordinary households should not be paying billions in added costs for data centers, yet that is what is highly likely to happen if PJM proceeds with its December auction that includes a massive amount of forecasted data center electric demand growth.”

PJM’s response, delivered by spokesman Jeffrey Shields to Utility Dive, is the position the grid operator has held since the price spike began: the cap is the safeguard, the demand is real, and delay is the risk. “The December auction includes an established price cap, providing an important safeguard against how high prices can rise,” Shields said. “Postponing the auction this close to its execution could destabilize the market and increase the risk of power interruptions when customers need electricity most.” The cap argument is half true. The cap bounds the price — no megawatt can clear above $337.83 per MW-day — but not the quantity, and the quantity is where the money is: at the reliability requirement of 158,712 MW, clearing at the cap implies a total auction cost on the order of $19.6 billion over the delivery year.

The destabilization claim is the strongest argument for proceeding, and it should not be dismissed. An auction scheduled to open December 9, with results posted December 22, is fourteen days from opening; market participants have positioned supply, credit, and hedging around that schedule, and moving it requires FERC approval and a new schedule. The July auction’s 6,831 MW shortfall is a real reliability gap, not a forecast artifact — postponing an auction does not postpone the load, it postpones the procurement.

The backstop that isn’t ready

The advocates ask for a separate reliability backstop procurement for the large loads — the mechanism PJM designed for exactly this purpose, a one-time 15-year contracting channel for the capacity the July auction failed to procure. But the backstop has been pushed back and will not happen before the December auction. FERC accepted the filing on September 29 and suspended it until February 28, 2027, pending a paper hearing; PJM refiled on October 29 with a far smaller target — roughly 630 MW, by the latest estimates — with a bid window of March 1–28, 2027 and results in May. The backstop exists because the July auction failed, it is delayed because FERC suspended it, and the December auction runs with the forecast load in it because the backstop is not there.

The same pattern holds across the parallel clocks. Exelon’s November 3 complaint at FERC, docketed as EL27-11, challenges the three-year-forward auction schedule partly over the uncertainty in forecasting data-center load, and asks the Commission to order PJM to move to a prompt capacity auction held two months before the delivery year, starting with the 2030/31 delivery year, and to rule by January 31. On November 16, PJM filed its tariff proposal responding to FERC’s June show-cause orders on large loads; the rules will shape how data-center load is treated for years, but they will not touch the December auction, which runs under the tariff as it stands. And on November 13, PJM convened a workshop on more than 30 papers responding to its May white paper — a multi-year redesign project by PJM’s own timeline. Every durable fix is on a clock that runs past the auction, and the auction is the one event that cannot wait.

The advocates also reach back to a commitment PJM itself made: a “statement of principles” endorsed in January by PJM and the governors of its 13 states, emphasizing that large-load forecasts must be “real and verified.” Proceeding with an auction that incorporates speculative data-center demand “would undermine that commitment and expose consumers to billions in potentially avoidable costs,” the letter says. The January principles were a political document, not a tariff rule, but the advocates are using them as PJM’s own standard — and a board that lets its own deadline pass without answering has not met it in the way the letter asked.

What the silence costs

The board is the body that is supposed to govern the tension between the states that pay for the market and the market that sets the price. A letter signed by the consumer advocates of seven states is not a stakeholder comment; it is the closest thing to a vote of no confidence the market’s own governance structure produces. Answering it late, or not at all, tells the signatories that the governance channel is not where the decision gets made. The next letter from those offices is less likely to be addressed to the board. It is more likely to be addressed to FERC.

What to watch

December 9 is the first date, and it is the one that decides the matter. If the auction opens on schedule, the letter becomes a record, and the argument moves to FERC. The three numbers to read first when the results post on December 22 are the clearing price, the shortfall against the 158,712 MW requirement, and the data-center load in the demand curve.

Before that, there are two things to watch in the days that remain. The first is whether the board answers at all. A late answer that directs a FERC filing would still be the only way the auction moves through PJM; a late answer that declines, or defers, would confirm what the silence already says. The second is whether any of the eight offices files at FERC. Ohio and Maryland have said they are weighing it, and a filing from the states is now the most plausible off-ramp left. The forecast is the fight now. The auction is only where it gets priced — and as of this morning, nobody has said the price will differ from the one the monitor predicted.