Eleven days. The Base Residual Auction for the 2029/30 delivery year opens December 9 and closes December 15, and as of this morning there is no public answer from PJM Interconnection’s Board of Managers to the letter eight consumer-advocate offices sent on November 18, asking the board to direct PJM to seek Federal Energy Regulatory Commission approval to postpone it. The advocates asked for a written answer by November 23. That deadline passed five days ago.

There is a fact about the calendar that reframes the silence. The board meeting everyone pointed to as the moment the question might be decided — November 17 — happened the day before the letter arrived. PJM’s own November 4 filing in the Exelon complaint docket said the board would consider “the path forward for the Base Residual Auction for the 2030/2031 Delivery Year” at that meeting. It said nothing about the December auction, because the postponement request did not exist yet. No board decision on the 2030/31 auction appears in the record either. The silence is not a board that met and declined. It is a board that has not met on the question.

What a postponement filing would have to survive

The board cannot postpone the auction itself. The auction calendar is in PJM’s tariff, so only FERC can move it. What the board can direct is a filing asking the Commission for a waiver of the tariff’s auction schedule. FERC could grant it, deny it, or sit on it — and sitting on it is, with eleven days left, the same as denying it. A waiver request filed this late would draw immediate intervention from generators, load-serving entities, and the states that did not sign the advocates’ letter — all of whom have already positioned supply, credit, and hedging around the published schedule.

PJM has itself described how high that bar is. In its November 4 preliminary answer in docket EL27-11, opposing fast-track treatment of Exelon’s complaint, PJM argued that fast-track processing requires a stringent showing — and that Exelon had not made one. That argument was about a different filing, but the standard it invokes is the one any emergency request to move the December auction would face. The Commission does not move scheduled auctions on a showing of controversy; it moves them on urgency that outweighs the disruption.

The states’ own route to FERC

The second route does not run through the board at all. The advocates themselves can go to FERC — a complaint, or a request for emergency relief — and both the Ohio and Maryland offices have said they are weighing action at the Commission if the board declines. As of this morning, no such filing has surfaced in the public record. The offices that said they were weighing a filing have not filed one, and the clock they would be filing against has lost five days since the deadline they set. A filing from the states would not need PJM’s cooperation, but it would arrive as an outsider’s request to halt a scheduled market, against PJM’s stated position that postponing “could destabilize the market and increase the risk of power interruptions when customers need electricity most” — spokesman Jeffrey Shields’s words to Utility Dive, which remain the grid operator’s only public position on the question.

There is a third possibility, and it is the one the record now points toward: the board answers late, in a way that neither directs nor declines — acknowledging the concern and deferring the structural question to the tariff process. That answer, if it comes now, changes nothing about December 9. The auction opens on schedule, the letter becomes a record, and the argument moves to FERC.

What the backstop would actually buy

The advocates’ alternative to the auction is a separate reliability backstop procurement for the large loads — the mechanism PJM designed for exactly this purpose. But what that procurement would actually buy is narrower than the phrase “backstop auction” suggests. The PJM State Legislators Collaborative, in its March 18 letter to the board, urged that eligibility be limited to new unforced capacity — “new UCAP that has not previously participated in the Base Residual Auction, including new generation, uprates, imports, and demand response” — with monitor oversight to ensure the capacity is genuinely incremental. Avoided retirements, the letter said, should not qualify: allowing them “could undermine that goal and lock in aging and expensive generation under long-term contracts.”

PJM’s own proposal took the same shape. The backstop, as filed, is a one-time procurement of new resources only, on commitments of up to 15 years. That is the design’s logic: the backstop exists to call forth new entry the capped auction cannot finance, not to re-price the existing fleet. A backstop that buys only new capacity is a different product from the December auction entirely — and that is why it cannot substitute for it on eleven days’ notice.

It also cannot substitute for it on the calendar. FERC accepted the backstop filing on September 29 and suspended it until February 28, 2027, pending a paper hearing on cost allocation, exit rules, and collateral requirements. PJM refiled on October 29 with a far smaller target — roughly 630 MW, by the latest estimates — with a bid window of March 1–28, 2027 and results in May. The backstop exists because the July auction failed. It is delayed because FERC suspended it. And the December auction runs with the forecast load in it because the backstop is not there.

The numbers the auction will price

The parameters have not moved either. The reliability requirement stands at 158,712 MW, the forecast peak load at 171,916 MW, and the collar at a $337.83 per MW-day cap with a $181.91 floor. The final planning parameters PJM was due to publish on November 19 — which could have removed canceled or delayed data-center projects from the demand curve — remain unlocated: one secondary account describes them as published on November 19, another reports that it could not find them. The October 29 parameters are the ones the auction will run against, with more than 20,000 MW of forecast data-center load still in the demand curve, per the monitor.

The monitor’s estimate of what that means has not changed either, and it should be stated with its conditions attached. Monitoring Analytics, in its November 12 State of the Market report, estimated that leaving the load in “effectively ensures that the auction will clear at the maximum price and add another $5 billion to $10 billion of data center related costs to all customers.” That is a forecast, not a result, contingent on the load staying in the forecast and the auction clearing at the cap. Both conditions are likely — the July auction for 2028/29 cleared at its $325 per MW-day cap in every zone — but neither is certain, and the range is the monitor’s, not PJM’s and not the advocates'.

The backward-looking number is the one that gives the estimate its weight. Including existing and forecast data-center load has already increased capacity costs by $29.4 billion across the four Base Residual Auctions already run, for the 2025/2026 through 2028/2029 delivery years — 46.2 percent of the $63.6 billion in total capacity charges. In the most recent auction alone, for 2028/2029, the monitor estimates $6.3 billion of $16.4 billion in charges was a result of data-center load. The monitor calls the $29.4 billion irreversible: those auctions have cleared, and no forecast revision can claw any of it back. PJM disputes the figure, saying the monitor’s total “does not equate to the total cost to load,” since a change in auction revenues is not the same as a change in what customers ultimately pay. That objection is fair as far as it goes. The monitor’s figure is a counterfactual — what capacity revenues would have been without data-center load in the demand curve.

The forecast is moving, and it cuts both ways

The monitor’s case is not that every forecast megawatt is phantom. The pipeline is shrinking where states have acted: AEP Ohio’s data-center pipeline fell from more than 30 GW to about 13 GW after regulators approved a tariff requiring large data centers to pay for at least 85 percent of the capacity they request, according to Utility Dive reporting. The monitor has documented that 4,017 MW — 42 percent — of the forecast increase in data-center load between the 2026/27 and 2028/29 delivery years had been canceled or delayed as of September 21. If only that canceled or delayed load is treated as never arriving, the July auction’s shortfall falls from 6,831.3 MW to 3,055.0 MW, a 55 percent reduction.

On the other side, real construction is under way: trade coverage citing Cleanview data showed developers began construction in the third quarter on 8.4 GW of data-center capacity at 65 buildings. The monitor’s case is that the forecast includes projects at every stage from breaking ground to a press release, with no discount for the difference — and that a three-year-forward auction cannot price that forecast without systematically overbuying. A refresh that catches canceled projects helps. It does not fix a rule that prices speculation at the same rate as steel in the ground. The household consequence is the one the advocates keep returning to: Maryland People’s Counsel David Lapp told the Daily Caller News Foundation that an on-schedule auction would keep data-center costs of more than $10 a month on bills. In the first nine months of 2026, wholesale power averaged $111.61 per MWh, up 40.9 percent from $79.19 a year earlier — and the monitor’s counterfactual puts $9.95 of that per MWh down to the capacity-market effect of data-center load alone.

What happens if the auction runs

The most likely outcome, on the evidence available this morning, is that it does. The auction is the fourth and final one under the price collar, and the monitor’s expectation is that it clears at the $337.83 cap. At the reliability requirement of 158,712 MW, clearing at the cap implies a total auction cost on the order of $19.6 billion over the delivery year. The results post December 22, and the three numbers to read first are the clearing price, the shortfall against the 158,712 MW requirement, and the data-center load in the demand curve.

The parallel clocks, and one that just moved

Every durable fix is still on a clock that runs past the auction, but one of those clocks moved this month. On November 13, FERC granted PJM’s request for more time to answer Exelon’s complaint in docket EL27-11 — the complaint that asks the Commission to replace the three-year-forward auction with a prompt auction held two months before delivery, starting with 2030/31. PJM’s answer, and all comments and interventions, are now due December 21, six days after the December auction closes. The prompt-auction fight is now formally a post-December question: whatever FERC eventually orders about the 2030/31 auction, it will be decided on a record that includes the December results, not before them. Exelon had supported an extension only to December 7; the Commission granted the full extension, and has not ruled on the fast-track request.

The other clocks have not moved, but they have gained voices. On November 5, public interest and environmental groups wrote to the board urging PJM to promptly refile its Interim Resource Adequacy Service proposal — rejected by FERC on October 9 — retaining the exclusion of certain large loads from the demand curve. At FERC’s recent open meeting, Commissioners See, Chang, and LaCerte all stressed that PJM should promptly develop a revised Section 205 filing. And a board-directed problem statement on “Connect and Manage” records wide agreement that connect-and-manage load should be excluded from the Base Residual Auction. On November 16, PJM filed its tariff proposal responding to FERC’s June show-cause orders on large loads, and on November 13 it convened a workshop on more than 30 papers responding to its May white paper. None of these touches the December auction, which runs under the tariff as it stands.

What to watch

Three dates, in order. The first is any day between now and December 9: a board answer that directs a FERC filing would still be the only way the auction moves through PJM, and a filing from the states would be the only way it moves without PJM. Either would have to land fast and survive immediate intervention. The second is December 9 itself, when the auction opens — and if it opens on schedule, the letter becomes a record and the argument moves to FERC. The third is December 22, when the results post: the clearing price, the shortfall, and the data-center load in the demand curve. The forecast is the fight now. The auction is only where it gets priced — and as of this morning, eleven days out, nobody with the power to change the price has said it will differ from the one the monitor predicted.