FRACMOO

Power, markets, flexible RA,and the money behind the grid

Nov 2026
U.S. electricity demand, 2026 f'cast4,306 TWh
Reserve margin (PJM 2028/29)14.7%
Interconnection queue2,061 GW

Advertisement

Topic

Load Growth

111 stories on this topic, across the desks.

Nov 28

DATA

TVA's $1.7 Billion Data-Center Deal Tests the Large-Load Tariff

Two weeks after the first $1.7 billion agreement under TVA's Capacity Commitment Charge, the tariff's real test is not whether developers will sign β€” it is what the money buys, and who pays if the load never arrives.

By Devon Park ·

Nov 27

INVESTING

The Capex Season Adds Up: CenterPoint Leads the Second Wave of Load-Growth Spending

CenterPoint Energy raised its ten-year capital plan to $70.7 billion and extended its earnings growth outlook through 2030, completing an earnings season in which five utilities announced roughly $342 billion of planned spending β€” and leaving one question for investors: what happens if the load arrives slower than the capex?

By Cole Bennett ·

Nov 25

INVESTING

The Suppliers' Quarter: The Load-Growth Thesis Arrives as Purchase Orders

Investors spent the fall pricing the utilities' $70–85 billion capital plans; the suppliers' order books are now the check on whether that build is real β€” 122 gigawatts of reserved gas turbines, a 900-megawatt fuel-cell deal, and a record year of generation behind them.

By Cole Bennett ·

Nov 21

INVESTING

Xcel's $70 Billion Plan Is Built to Survive Without the Data Centers

Xcel Energy's $70 billion five-year capital plan is one of the largest regulated buildouts of the season β€” and its most interesting feature is what it does not depend on: the base plan stands on existing customer needs, leaving the data-center bet in a $10 billion layer of optionality on top.

By Cole Bennett ·

Nov 21

GRID

FERC's November Meeting: Build the Wires, but Prove Every Dollar in the Rate

At its November 19 open meeting, FERC authorized the affiliate sales behind NIPSCO's data-center buildout and sustained the incentives for a $1.7 billion transmission line β€” while sending New England transmission owners to hearing over the employee bonuses in their rates.

By Mara Ellison ·

Nov 20

INVESTING

Southern's $85 Billion Bet: The Load-Growth Thesis Arrives in the Numbers

Southern Company's third quarter turned the data-center load wave into a 21% earnings jump, a guidance raise, and a capital plan that now runs to roughly $85 billion β€” and the question for investors is whether the load arrives on schedule or the bill lands on ratepayers.

By Cole Bennett ·

Nov 20

MARKETS

The Forecast Is the Fight Now: Seven States Ask PJM to Delay December's Capacity Auction Over Phantom Data Centers

Eight ratepayer-advocate offices in seven states joined PJM's market monitor on Wednesday in asking the grid operator's board to postpone the 2029/30 capacity auction until data-center load is stripped from the forecast β€” arguing the auction would otherwise price load that may never arrive, at an estimated $5–10 billion to consumers.

By Priya Raman ·

Nov 20

GRID

The Sixth Filing: SPP Closes the Set on FERC's Large-Load Orders

Southwest Power Pool's response to FERC's large-load show-cause order is due today, completing the six-operator set β€” and unlike the other five, SPP is mostly defending a framework FERC has already accepted.

By Mara Ellison ·

Nov 17

GRID

The Bridge Is the Answer: What the Grid Operators Told FERC About Large Loads

Five grid operators owed FERC their large-load answers on November 16, and the filings in public view converge on the same bargain β€” connect early on available capacity, accept curtailment, and graduate to firm service β€” while SPP, due Friday, already has the template.

By Mara Ellison ·

Nov 13

GRID

The Grid Is Better Prepared for Winter. The Next Storm Will Be the Test.

NERC's cold-weather data shows 99 percent of winter capacity can operate at extreme cold temperatures, and the January Arctic storms proved the preparation works β€” but corrective action plans still hang open, and demand keeps rising into every margin the grid has bought.

By Mara Ellison ·

Nov 10

MARKETS

Five Standards, One Deadline: NERC's Large-Load Rules Head to FERC

The Board's October 26 adoption of three new computational-load standards and two facility-interconnection revisions moves the reliability half of the large-load response into FERC's hands β€” with a December 31 filing deadline, a November 20 comment date, and years of phased compliance still ahead.

By Priya Raman ·

Nov 9

MARKETS

PJM's Backstop Was Built for 6.8 GW. The Forecast Now Says It May Buy 630 MW.

The refiled March procurement still carries a $555/MW-day ceiling and 15-year terms, but utilities' lowered load forecasts have cut the gap it was designed to fill by more than nine-tenths β€” and Exelon's new complaint asks whether the three-year auction that created the gap should exist at all.

By Priya Raman ·

Nov 7

INVESTING

Riot Platforms' $28 Billion Lease With Anthropic

A bitcoin miner is becoming an AI infrastructure landlord β€” and the fine print of its Corsicana lease shows exactly what that transformation costs.

By Cole Bennett ·

Nov 7

GRID

497 Actions, One Question: How States Plan for Large Loads

NCCETC counted 497 state actions on power decarbonization and resource planning in Q3 β€” and the dominant story is large load moving from the tariff docket into the integrated resource plan.

By Mara Ellison ·

Nov 5

INVESTING

Dominion's Q3 Makes the Merger Math Legible

Regulated earnings surged, a nonregulated write-down landed, and Virginia's evidentiary hearing on the NextEra deal opens in twelve days.

By Cole Bennett ·

Nov 4

MARKETS

PJM Now Has Two Answers to the Same Question, and Both Run Into the Same Auction

Charles River Associates' independent forecast sees PJM data-center demand reaching 30 GW by 2030 with an 11.5 GW gap to what can be powered at 1-in-10 reliability, while utilities' lowered near-term forecasts could shrink the refiled backstop from 6.8 GW to roughly 630 MW β€” and both answers feed the same December auction and March procurement.

By Priya Raman ·

Oct 31

INVESTING

Exelon's $0.87 Beat and the Transmission Story Behind It

Exelon beat consensus and narrowed guidance on the strength of approved rates, then pointed to $12–17 billion of transmission and $3–7 billion of storage beyond its $41.7 billion plan β€” upside that only becomes rate base if regulators and grid planners say yes.

By Cole Bennett ·

Oct 28

INVESTING

FirstEnergy's $0.98 Beat and the Load-Growth Question Behind It

FirstEnergy beat consensus by eight cents and reaffirmed guidance toward the high end of its growth range β€” but the number that matters most is 7.9 gigawatts of contracted large-load demand, and whether it becomes rate base on schedule.

By Cole Bennett ·

Oct 28

DATA

Three Utilities, Three Answers: Indiana's Data-Center Cost Experiment

The IURC's unanimous approval of AES Indiana's plan to serve Google's 390 MW Monrovia campus is the first test of the state's 2025 large-load law β€” and it sits alongside two very different Indiana models for making a hyperscaler pay.

By Devon Park ·

Oct 27

INVESTING

CBRE's Billion-Dollar Bet on Data-Center Execution

CBRE will pay up to $1 billion for Onnec, betting that the scarce resource in the data-center buildout is no longer capital or power, but the crews that install the infrastructure on time, identically, everywhere.

By Cole Bennett ·

Oct 15

DATA

Texas Hit Pause on 474 GW: What the ERCOT Audit Is Actually Checking

ERCOT was tracking roughly 474 GW of large-load requests β€” about 90 percent data centers, more than five times the state's record peak β€” so Texas stopped approving new connections and started verifying which projects are real.

By Devon Park ·

Oct 15

GRID

How SPP's CHILLS Service Answered the Problem That Killed PJM's IRAS

Months before FERC rejected PJM's curtailment framework, it accepted SPP's conditional transmission service β€” a voluntary, transmission-based bargain that lets large loads connect fast and be interrupted when the wires bind.

By Mara Ellison ·

Oct 9

DATA

Google's 890 MW Nuclear Uprate Deal, Explained

Google will underwrite 890 megawatts of nuclear uprates at eleven existing reactors β€” the fastest credible path to the firm, carbon-free power its AI buildout demands.

By Devon Park ·

Oct 6

INVESTING

Data-Center Power as an Asset Class

Hyperscale load is turning electricity supply into contracted infrastructure β€” how investors underwrite the electrons behind the cloud.

By Cole Bennett ·

Advertisement